Difference between revisions of "Photon Beam Commissioning Discussion July 23, 2014"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 30: Line 30:
 
##Cross Calibration Procedure for absolute current measurement desired?
 
##Cross Calibration Procedure for absolute current measurement desired?
 
##Point of contact in Radcon for measurement test plan for fall? (George or Pavel perhaps?)
 
##Point of contact in Radcon for measurement test plan for fall? (George or Pavel perhaps?)
##Regarding minimum deliverable current:  
+
##Regarding minimum deliverable current (open question from last time):  
 
{| class="wikitable" style="text-align: center; color: black;"
 
{| class="wikitable" style="text-align: center; color: black;"
 
|Stripline BPM Resolutions
 
|Stripline BPM Resolutions

Revision as of 13:21, 23 July 2014

Organization

  • Time: 4 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Alexandre for Hall D)

Agenda

  1. Announcements
  2. Electron Commissioning (Todd/Mike)
    1. Hall D Beam Delivery Procedure heading to Rev. 10 with feedback received.
    2. Ion Chamber Procedures currently under review for release for use.
    3. Eugene/Curtis added as administrators for Hall D Operational Restrictions[1]
    4. System Experts requested to write test plans for nA BPM, FFB, and Active Collimator hardware commissioning.
    5. Cross Calibration Procedure for absolute current measurement desired?
    6. Point of contact in Radcon for measurement test plan for fall? (George or Pavel perhaps?)
    7. Regarding minimum deliverable current (open question from last time):
Stripline BPM Resolutions ≥ 30nA 100um resolution < 30nA resolution suffers(position noisy barring additional filtering) 3nA yields expected resolution ≈ 300 µm
  1. Photon Commissioning Draft (Alexandre)
  2. Radiation monitors
  3. Aug 8 Review:
  4. Other business

Minutes

Attending:'