Difference between revisions of "Photon Beam Commissioning Discussion July 23, 2014"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 27: Line 27:
 
##Ion Chamber Procedures currently under review for release for use.
 
##Ion Chamber Procedures currently under review for release for use.
 
##Eugene/Curtis added as administrators for Hall D Operational Restrictions[http://opsweb.acc.jlab.org/internal/ops/ops_webpage/restrictions/ops_restrictions.html]
 
##Eugene/Curtis added as administrators for Hall D Operational Restrictions[http://opsweb.acc.jlab.org/internal/ops/ops_webpage/restrictions/ops_restrictions.html]
##System Experts requested to write test plans  
+
##System Experts requested to write test plans for nA BPM, FFB, and Active Collimator hardware commissioning
 
# Photon Commissioning Draft (Alexandre)
 
# Photon Commissioning Draft (Alexandre)
 
# Radiation monitors
 
# Radiation monitors

Revision as of 12:54, 23 July 2014

Organization

  • Time: 4 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Alexandre for Hall D)

Agenda

  1. Announcements
  2. Electron Commissioning (Todd/Mike)
    1. Hall D Beam Delivery Procedure heading to Rev. 10 with feedback received.
    2. Ion Chamber Procedures currently under review for release for use.
    3. Eugene/Curtis added as administrators for Hall D Operational Restrictions[1]
    4. System Experts requested to write test plans for nA BPM, FFB, and Active Collimator hardware commissioning
  3. Photon Commissioning Draft (Alexandre)
  4. Radiation monitors
  5. Aug 8 Review:
  6. Other business

Minutes

Attending:'