* <strike> Send link to accelerator commissioning procedure (Mike) </strike> | * <strike> Send link to accelerator commissioning procedure (Mike) </strike> | ||
− | * Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations ( | + | * Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this |
− | * Todd will provide the magnetic field of the quadrupole immediately upstream of the tagger magnet (Todd) | + | * <strike> Todd will provide the magnetic field of the quadrupole immediately upstream of the tagger magnet (Todd) </strike> Todd has requested the information and will pass it on when he gets it |
− | * Check that radiator set for commissioning is available (Alexandre, Hovanes) | + | * <strike> Check that radiator set for commissioning is available (Alexandre, Hovanes) </strike> Material for 2x10^-4 available, Alexandre will order the 1x10^-4 material |
− | * Check that RadCon detectors are available/installed in tagger hall and hall D (Alexandre) | + | * <strike> Check that RadCon detectors are available/installed in tagger hall and hall D (Alexandre) </strike> Draft plan with Radcon is in place and will be pursued |
− | * Check that 'rapid access system' is being implemented in Hall D (Alexandre) | + | * <strike> Check that 'rapid access system' is being implemented in Hall D (Alexandre) </strike> Draft plan with RadCon is in place and will be pursued. |
− | * Organize preparations for review (Elton). | + | * <strike> Organize preparations for review (Elton). </strike> See notes |
== Agenda == | == Agenda == |
Revision as of 18:01, 16 July 2014
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
- Hall D Commissioning Pages
- DRAFT Accelerator Hall D Beam Delivery Procedures(V.1b9)
- DRAFT Accelerator Tagger Magnet Operation Procedures(V. 0)
- DRAFT Accelerator Hall D Ion Chamber Functional Test Procedure(V.1b3)
- DRAFT Accelerator Hall D Ion Chamber Calibration Procedure(V.1b2)
Action Items
-
Send link to accelerator commissioning procedure (Mike) - Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
-
Todd will provide the magnetic field of the quadrupole immediately upstream of the tagger magnet (Todd)Todd has requested the information and will pass it on when he gets it -
Check that radiator set for commissioning is available (Alexandre, Hovanes)Material for 2x10^-4 available, Alexandre will order the 1x10^-4 material -
Check that RadCon detectors are available/installed in tagger hall and hall D (Alexandre)Draft plan with Radcon is in place and will be pursued -
Check that 'rapid access system' is being implemented in Hall D (Alexandre)Draft plan with RadCon is in place and will be pursued. -
Organize preparations for review (Elton).See notes
Agenda
- Announcements
- Electron Commissioning (Todd/Mike)
- Photon Commissioning Draft (Alexandre)
- Aug 8 Review: Location CC L102
- Reviewers: Mike Spata, Brian Freeman, Stepan Stepanyan
- Charge/Schedule (Elton/Eugene)
- Materials: Accelerator Procedures (Mike); Plan for photon beam commissioning (Alexandre)
- Talks: Overview/Goals/Charge (Eugene); Photon beam properties (Richard); Electron beam commissioning (Michael); Photon beam commissioning (Alexandre)
- Other business
Minutes
- Attending: