OWG meeting 14-Dec-2007

From GlueXWiki
Revision as of 16:17, 17 December 2007 by Wolin (Talk | contribs)

Jump to: navigation, search

Agenda


Time/Location

2:00pm Fri 14-Dec-2007 Cebaf Center F326

To connect by telephone:

1) dial:
+1-800-377-8846 : US
+1-888-276-7715 : Canada
+1-302-709-8424 : International

2) enter participant code: 39527048# (remember the "#")


Announcements

  • Minor rewording in Wiki pages: DAQ/Online/Controls ==> Trigger/DAQ/Monitoring/Controls.
  • Suggestion to form Hall D electronics pool.


Next Meeting

Next meeting will be in Jan, date TBD.


New Action Items from this Meeting

  • Add to online milestones document (Elliott):
    • more specific electronics milestones
    • demonstration of full crate-sum trigger readout
    • add dates for each milestone
  • Give Elke items for the Hall D Action Item Tracker (Elliott)
    • more detailed than major milestonen
    • include names, dates, etc.


Minutes

Attendees: Elliott W, Dave A, Chris C, Fernando B, Mark I, Elton S, Dave D, Ed J, Carl T, Simon T.


Chris Cuevas gave an update on electronics:

  • Many specs and drawings in draft state, prototypes are coming.
  • Manpower is a big problem given deadlines, esp. for the crate-sum module.
  • Two more 20-slot VXS crates on order.
  • Slightly behind on FADC October milestones, no full crate tests yet.
  • Hai will work on FADC after completing an Accelerator project.
  • New hire will arrive in Jan, will work on VXS backplane clock distribution.
  • Some discussion ensued concerning what must be demonstrated for the subsystem and CD-3 reviews.
    • critical items not yet demonstrated.
  • More discussion about subsystem review May 2008, scope is what has not been previously reviewed (Trigger, DAQ, etc).
    • CD-3 (Lehman) review will view reports of other subsystem reviews, but likely will not probe more deeply.


Chris discussed results of manpower meeting with Claus et al:



Dave Doughty discussed how to include the tagger in the trigger:

Elliott presented the list of online major milestones: