* Reviewed minutes from last meeting
 +
* Discussed updated radiation model based on latest geometry
 +
** Keith to supply absorber geometry and steel around it to Pavel
 +
** Stephanie gave magnet dimensions to Pavel, for coils, Cu/H2O ratio is 56/44
 +
* Looked at Z locations in Tagger hall
 +
** May be space to move upstream some amount if needed
 +
** need space for Halo monitors upstream of radiator (maybe 8cm beampipe)
 +
* Will continue with plans to use air castors to move assy
 +
* Onish had a power supply reveiw this week, all is still on track for March 2025 delivery
 +
* DeGauss test
 +
** Onish collecting parts and info for reversing switch for Mag measurement power supply
 +
* Magnet update
 +
** Pavel will look at radiation levels to determine if less rad-hard resin can be used
 +
** Plan on using copper dump skid for cooling magnet to utilize ALARA principles
 +
* Pavel asked about shielding downstream of permanent magnet, we will address that in the near future. We are concentrating on the  center absorber/shielding section
 +
* Lead brick painting bids due in May 14
 +
* June - items due from ERR
 +
** Thermal cycling of tungsten and copper write up - in work (Tim)

Latest revision as of 16:11, 7 May 2024

Meeting Time and Place

Tuesday, May 07, 2024, 1:00pm Hall D Counting House

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard

Agenda

Minutes

  • Reviewed minutes from last meeting
  • Discussed updated radiation model based on latest geometry
    • Keith to supply absorber geometry and steel around it to Pavel
    • Stephanie gave magnet dimensions to Pavel, for coils, Cu/H2O ratio is 56/44
  • Looked at Z locations in Tagger hall
    • May be space to move upstream some amount if needed
    • need space for Halo monitors upstream of radiator (maybe 8cm beampipe)
  • Will continue with plans to use air castors to move assy
  • Onish had a power supply reveiw this week, all is still on track for March 2025 delivery
  • DeGauss test
    • Onish collecting parts and info for reversing switch for Mag measurement power supply
  • Magnet update
    • Pavel will look at radiation levels to determine if less rad-hard resin can be used
    • Plan on using copper dump skid for cooling magnet to utilize ALARA principles
  • Pavel asked about shielding downstream of permanent magnet, we will address that in the near future. We are concentrating on the center absorber/shielding section
  • Lead brick painting bids due in May 14
  • June - items due from ERR
    • Thermal cycling of tungsten and copper write up - in work (Tim)