(Tentative Agenda)
(Items for followup from previous meeting(s))
Line 13: Line 13:
 
# Fcal
 
# Fcal
 
#* Decision on rad hard detectors
 
#* Decision on rad hard detectors
 +
#* Matt to coordinate with Christina on the shipment of glass blocks and pmts/dividers for monitoring system test.
  
 
= Documents to Review=
 
= Documents to Review=

Revision as of 14:51, 4 March 2010

Teleconference Time: 11:00 a.m. EST

  • ESNET and EVO session
  • Phone in CC F326 is 757-269-6337
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Fcal
    • Decision on rad hard detectors
    • Matt to coordinate with Christina on the shipment of glass blocks and pmts/dividers for monitoring system test.

Documents to Review

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring
  4. FCAL
  5. BCAL
  6. Other business

Minutes

Attendees:

  1. BCAL
    1. Construction
      1. All equipment operating nominally. Builds growing within tolerances.
      2. Mod 04 to RMS today or tomorrow; Mod 05 at 50%, Mod 06 at 10%. Two new crates arrived yesterday.
      3. Mod 02 and 03 machining most likely finished.
      4. Lead tally nearly done; some discrepancies. Will communicate with JLab and Vulcan today.
      5. Enough epoxy for 2.5 months on hand, 9 gallons back ordered.
      6. Shipping insurance sorted out and waiting to meet with shippers and get new quotations.
    2. Fibres
      1. Shipment 8 done and 100 fibres from No. 9 (see above links). Means shifted for shipment 9, for both Npe and atten length. Most likely a real effect but we're checking.
    3. RMS visit: March 5.
      1. Final contract will be given to RMS tomorrow.
      2. Inspection and pictures of Mod 02 and 03 machining.
      3. Transmission uniformity test on Module 01.