Difference between revisions of "Mar 18, 2010 Calorimetry"

From GlueXWiki
Jump to: navigation, search
(Items for followup from previous meeting(s))
(Tentative Agenda)
Line 20: Line 20:
 
# Announcements
 
# Announcements
 
# Review of Action Items
 
# Review of Action Items
# Calibration/Monitoring  
+
# Calibration/Monitoring
## Light sources in Bcal
+
## Project schedule
+
##* FCAL activity Fab monitoring system 15222080 (delayed by a year in Oct)
+
##* BCAL activity Proc aux equipment incl. calibration 15221055
+
 
# FCAL
 
# FCAL
## Radiation Damage Inserts
 
##* Shashlyk option
 
## Procurement Contract
 
##* EVMS reporting and project schedule
 
##* Scheduling the [[Fcal Fabrication Readiness Review]]
 
## Update on FEU-84-3 PMTs [[media:Feu_pmt_melz.pdf|slides]]
 
 
# BCAL
 
# BCAL
## Construction Status
 
## Fibre tests [[Media:Shipments8and9plots.pdf]]
 
# BCAL Readout
 
## Simulations
 
## SiPMs
 
##* [http://www.jlab.org/Hall-D/software/wiki/images/1/1a/HAMAMATSU3x3.pdf Measurements at USM]
 
## Geometry for guides, sensors, cooling and cables
 
## Update on USM MOU
 
 
# Other business
 
# Other business
  

Revision as of 14:37, 4 March 2010

Teleconference Time: 11:00 a.m. EST

  • ESNET and EVO session
  • Phone in CC F326 is 757-269-6337
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Fcal
    • Decision on rad hard detectors

Documents to Review

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring
  4. FCAL
  5. BCAL
  6. Other business

Minutes

Attendees:

  1. BCAL
    1. Construction
      1. All equipment operating nominally. Builds growing within tolerances.
      2. Mod 04 to RMS today or tomorrow; Mod 05 at 50%, Mod 06 at 10%. Two new crates arrived yesterday.
      3. Mod 02 and 03 machining most likely finished.
      4. Lead tally nearly done; some discrepancies. Will communicate with JLab and Vulcan today.
      5. Enough epoxy for 2.5 months on hand, 9 gallons back ordered.
      6. Shipping insurance sorted out and waiting to meet with shippers and get new quotations.
    2. Fibres
      1. Shipment 8 done and 100 fibres from No. 9 (see above links). Means shifted for shipment 9, for both Npe and atten length. Most likely a real effect but we're checking.
    3. RMS visit: March 5.
      1. Final contract will be given to RMS tomorrow.
      2. Inspection and pictures of Mod 02 and 03 machining.
      3. Transmission uniformity test on Module 01.