Difference between revisions of "JEF meeting, march 1, 2024"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 9: Line 9:
 
** - signal cables -  done
 
** - signal cables -  done
 
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done
 
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done
** - HV cables: received 165 cables 1445 in total
+
** - HV cables: received all cables
 
** - HV distribution boards: in preparation
 
** - HV distribution boards: in preparation
 
** - LV cables: 100 cables received, 250 cables in total
 
** - LV cables: 100 cables received, 250 cables in total
Line 31: Line 31:
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
** Installation of the LMS  
 
** Installation of the LMS  
*** 175 fibers installed during this week (488 in total) [https://logbooks.jlab.org/entry/4253130] [https://logbooks.jlab.org/entry/4249236]
+
*** 312 fibers installed during this week (800 in total) [https://logbooks.jlab.org/entry/4253130] [https://logbooks.jlab.org/entry/4249236]
 
** Cable and divider installation [https://logbooks.jlab.org/entry/4249243][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable2.jpg]
 
** Cable and divider installation [https://logbooks.jlab.org/entry/4249243][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable2.jpg]
 
** Still no power on the ECAL platform  (expect delay with the development of the trigger/DAQ)
 
** Still no power on the ECAL platform  (expect delay with the development of the trigger/DAQ)
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''
** [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6347 Rough draft of Feb. collaboration talk] -- Simon
 
 
** [https://halldweb.jlab.org/wiki/images/1/1e/Glue-jefxd-igal-jaegle-16042024.pdf updates] -- ig
 
** [https://halldweb.jlab.org/wiki/images/1/1e/Glue-jefxd-igal-jaegle-16042024.pdf updates] -- ig

Revision as of 10:11, 1 March 2024

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received all cables
    • - HV distribution boards: in preparation
    • - LV cables: 100 cables received, 250 cables in total
    • - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
    • - Optical fibers and parts for the trigger/DAQ have been ordered
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [6]
    • - About 1100 dividers have been fabricated
    • - Started removing power regulators on the newly fabricated dividers
    • - George has tested 133 + 41 = 174 dividers (811 tested in total) [7].
    • - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
    • Detector installation [8][9][10]
    • Installation of the LMS
      • 312 fibers installed during this week (800 in total) [11] [12]
    • Cable and divider installation [13][14][15]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page
  • Analysis/Simulation