Difference between revisions of "JEF meeting, September 16, 2022"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
 
Line 7: Line 7:
 
* Simulations/Analysis
 
* Simulations/Analysis
 
* Preparation of parts for FCAL2 modules -- Sasha
 
* Preparation of parts for FCAL2 modules -- Sasha
** Received 100 PMTs (the last batch) [https://halldweb.jlab.org/wiki-private/index.php/PMT_for_FCAL_insert]
 
*** All PMTs have been checked (measured diameter)
 
*** 39 PMTs were traded in with the NPS (they are slightly tight)
 
 
** Crystals.   
 
** Crystals.   
 
*** [https://halldweb.jlab.org/wiki/index.php/CRYTUR 45 CRYTUR crystals received from Physics division]
 
*** [https://halldweb.jlab.org/wiki/index.php/CRYTUR 45 CRYTUR crystals received from Physics division]

Latest revision as of 10:43, 30 September 2022

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

Minutes

Attendees: Bill, Arshak, Axel, Sasha, Phil, Jane, Igal, Jon, Liping, S.T.

  • Received another 48 Crytur crystals (out of 150)
  • Expect 70 more from subsequent orders
  • Detector support group working on wrapping crystals
  • Only need about 200 light guides
  • Expect 100 PMTS this month
  • Received 75 PMT housings
  • Waiting for brass straps
  • Grand total fabricated modules = 1221, 77 more crystals ready for fabrication
  • Installation meetings will resume week of 9/19/22
    • Discussed patch panels for signal cables (with lemo connectors)
  • Week of 9/19/22: Sasha to resume PMT divider bench tests
    • Dividers need to ordered in October