Difference between revisions of "JEF meeting, September 16, 2022"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 10: Line 10:
 
*** [https://halldweb.jlab.org/wiki/index.php/CRYTUR 45 CRYTUR crystals received from Physics division]
 
*** [https://halldweb.jlab.org/wiki/index.php/CRYTUR 45 CRYTUR crystals received from Physics division]
 
*** currently available/ordered + CCAL:  1593 + (9) + 20 (recent order) =  1622  (may need to order more spares (?) )
 
*** currently available/ordered + CCAL:  1593 + (9) + 20 (recent order) =  1622  (may need to order more spares (?) )
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg]. Remaining components:
+
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts]
*** 300 brass assemblies (Keith and Chris will continue to work on them,  waiting for straps)
+
 
*** 200 light guides, will be delivered during a couple of next weeks.
+
*** 400 PMT housings, expect to receive during next two months (bottleneck now)
+
 
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals:] 682  
 
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals:] 682  
 
*** <span style="color:#FF0000"> All currently available </span>
 
*** <span style="color:#FF0000"> All currently available </span>

Revision as of 08:37, 16 September 2022

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

    • Wrapped CRYTUR crystals: 682
      • All currently available
    • Meeting with the DSG group: Mindy and George will continue working on the project in September
  • Module fabrication -- Sasha
    • Received 72 + 76 PMT housings from Tim
    • Status of fabrication
    • Fabricated modules: Total 1206 (a new milestone)
    • Clean room EEL126 [1][2]
      • Expect to move to the new lab EEL108 (the same building) [3]
      • Work on amending safety docs
    • All students will leave during this week (11 students have been working on the project during this summer)
      • Great job !
      • (had also a chance to work on the CCAL project [4])
  • Updates from the FCAL installation meetings with Tim's group -- Sasha


  • Preparation of parts for FCAL2 modules -- Sasha
  • Module fabrication -- Sasha
  • Light Monitoring System -- Arshak