Difference between revisions of "JEF meeting, October 19, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 24: | Line 24: | ||
** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ||
** Detector survey | ** Detector survey | ||
+ | ** Installation of racks [https://halldweb.jlab.org/detectors/fcal2/cables/racks/install_racks1.jpg][https://halldweb.jlab.org/detectors/fcal2/cables/racks/install_racks2.jpg] | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] |
Revision as of 09:06, 20 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: all cables are ready. 240 have been labeled during this week.
- - signal patch panels are ready [1]
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: check HV distribution boards during this week. Chris is finalizing design of the distribution board, should order 4 boards soon.
- - LV cables: ordered, lead time unclear
- - LV distribution boards: met with Chris and Stephanie on Monday last week. The design of the LV distribution board has been fixed.
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- Tested and labeled ~240 short signal cables (Recently labeled cables in boxes)
- Final inspection of installed lead glass and lead tungstate modules [https://logbooks.jl
- Summer Students (2023)
- Prepare modules for the TAC and prototypes (using crystals with some imperfections) [2]
- Testing of PMT dividers -- Sasha / Vlad
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Plastic caps have been glued to all fibers
- Returning low-quality crystals to SICCAS -- Sasha
- 11 crystals were wrapped and placed into the box; they are ready for shipment to SICCAS [12]
- Analysis/Simulation
- First look at impact of GEMTRD -- Simon