Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV short cables: received, checked, labeled (last week)
    • - HV long cable, 18 ready (out of 36)
    • - HV distribution boards: in preparation
    • - LV cables: 150 cables received, 400 cables in total
    • - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
  • Ongoing projects -- Sasha, all
    • - Tested and labeled all HV cables ! and about 100 LV cables -- Laveen
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [3]
    • - About 1300 dividers have been fabricated (Chris, Armen, Mindy)
    • - Started removing power regulators on the newly fabricated dividers
    • - George has tested 41 dividers (865 have been tested in total) [4].
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
  • Analysis/Simulation

Minutes

Attendees: Bill, Sasha, Igal, Laveen, Phil, Jon, Zisis, Vlad, Stjepan, Liping, Jane, S.T.

  • All short HV cables have arrived and have been tested and labeled
  • Fabrication of long HV cables with Radiall connectors ongoing (18 out of 36)
  • Short LV cables continue to arrive, current inventory has been checked and labeled
  • Still need 250 PMT dividers; 865 have been tested
  • LMS installation ongoing at ~80 fibers/day; 1053 installed
  • Power has finally been installed for ECAL racks
    • Waiting for ethernet connection; parts for patch panel for trigger on order
  • Laveen to start working on software/xml specification for geometry
  • Igal working with Daniel L.: machine learning tools/framework
    • Phil will provide a master's student to work with Igal
  • Calibration discussion
    • Plan is to install layers of PMT dividers, make light tight and start checking row-by-row using LMS
      • Voltage calibration curves, use results from 5x5 prototype for guidance in setting HV
    • Set up self-trigger, look for cosmics
      • Might also set up scintillator paddles for triggering
    • Then with beam: Compton + pi0 events, study with MC first