JEF meeting, March 8, 2024

From GlueXWiki
Revision as of 10:11, 8 March 2024 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV short cables: received, checked, labeled (last week)
    • - HV long cable, 18 ready (out of 36)
    • - HV distribution boards: in preparation
    • - LV cables: 150 cables received, 400 cables in total
    • - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
  • Ongoing projects -- Sasha, all
    • - Tested and labeled all HV cables ! and about 100 LV cables -- Laveen
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [3]
    • - About 1300 dividers have been fabricated (Chris, Armen, Mindy)
    • - Started removing power regulators on the newly fabricated dividers
    • - George has tested 133 + 41 = 174 dividers (811 tested in total) [4].
    • - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
    • Detector installation [5][6][7]
    • Installation of the LMS
      • 312 fibers installed during this week (800 in total) [8]
    • Cable and divider installation [9][10][11]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page