Line 10: Line 10:
 
** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. Have to populate with connectors, and design a box around the PCB
 
** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. Have to populate with connectors, and design a box around the PCB
 
* '''Ongoing projects''' -- Sasha / Vlad / Hakob / Laveen
 
* '''Ongoing projects''' -- Sasha / Vlad / Hakob / Laveen
** - Tested  and labeled all HV cables ! and about  100 LV cables  
+
** - Tested  and labeled all HV cables ! and about  100 LV cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_labling.jpg]
 
** - Bundling short cables (groups of 7, 7, and 6 cables)
 
** - Bundling short cables (groups of 7, 7, and 6 cables)
 
*** finished:  LV - 13 layers, HV - 17 layers, signal - 6 layers  (36 in total out of 120) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls2.jpg]
 
*** finished:  LV - 13 layers, HV - 17 layers, signal - 6 layers  (36 in total out of 120) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls2.jpg]

Revision as of 09:35, 21 March 2024

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV short cables: received, checked, labeled (last week)
    • - HV long cable, 18 ready (out of 36)
    • - HV distribution boards: in preparation
    • - LV cables: 100 cables received, 500 cables in total
    • - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
  • Ongoing projects -- Sasha / Vlad / Hakob / Laveen
    • - Tested and labeled all HV cables ! and about 100 LV cables [3]
    • - Bundling short cables (groups of 7, 7, and 6 cables)
      • finished: LV - 13 layers, HV - 17 layers, signal - 6 layers (36 in total out of 120) [4][5]
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [6]
    • - About 1420 dividers have been fabricated (Chris, Armen, Mindy)
    • - Started removing power regulators on the newly fabricated dividers
    • - George has tested 54 dividers (919 have been tested in total) [7].
    • - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
  • Analysis/Simulation