Line 17: | Line 17: | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George | ||
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ||
− | ** - About | + | ** - About 1400 dividers have been fabricated (Chris, Armen, Mindy) |
** - Started removing power regulators on the newly fabricated dividers | ** - Started removing power regulators on the newly fabricated dividers | ||
** - George has tested 41 dividers (865 have been tested in total) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. | ** - George has tested 41 dividers (865 have been tested in total) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. |
Revision as of 09:04, 15 March 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV short cables: received, checked, labeled (last week)
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 500 cables in total
- - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
- Ongoing projects -- Sasha, all
- - Tested and labeled all HV cables ! and about 100 LV cables -- Laveen
- Testing of PMT dividers -- Sasha / Vlad / George
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Analysis/Simulation