Difference between revisions of "JEF meeting, February 3, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 9: | Line 9: | ||
*** Expect to receive 95 more CRYTUR crystals in May (835 + 95 = 930 in total) | *** Expect to receive 95 more CRYTUR crystals in May (835 + 95 = 930 in total) | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 835 (ALL available CRYTUR) ] | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 835 (ALL available CRYTUR) ] | ||
− | *** Available for wrapping: | + | *** Available for wrapping: 60 SICCAS crystals from CCAL && prototype [https://halldweb.jlab.org/wiki/index.php/All_modules_(with_SICCAS_crystals)_are_removed] [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/ccal_crystals.pdf] |
*** George (DSG group) started disassembling CCAL modules and removing LMS caps. | *** George (DSG group) started disassembling CCAL modules and removing LMS caps. | ||
*** Mindy (DSG group) continues wrapping crystals and soldering wires to sockets | *** Mindy (DSG group) continues wrapping crystals and soldering wires to sockets |
Revision as of 05:43, 3 February 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Received all 150 CRYTUR crystals from physics division (22-C0275) [1]
- Expect to receive 95 more CRYTUR crystals in May (835 + 95 = 930 in total)
- Wrapped CRYTUR crystals: 835 (ALL available CRYTUR)
- Disassembling CCAL
- CCAL moved to the ESB
- All modules (with SICCAS crystals) are removed
- List of available parts
- Some PMT housing are missing ( > 60, trying to find with Tim)
- Received all 150 CRYTUR crystals from physics division (22-C0275) [1]
- Module fabrication -- Sasha
- Fabricated modules: Total 1420 (7 modules fabricated since last week)
- Testing of PMT dividers -- Sasha / Arshak
- Most parts for dividers have been received
- 25 dividers for the prototype are ready (have to be tested), expect to receive the LV patch panel prototype
during next week. The CCAL prototype should be ready by the end of next week (?)
- Installation of the FCAL2 detector -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group
- Manpower and division of tasks
- Projects for summer students
- Meeting with the detector imaging group
- Light Monitoring System -- Arshak
- Simulations/Analysis