Difference between revisions of "GlueX Target Design Review, February 8, 2013"
From GlueXWiki
(Created page with "Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch, ==Review Slides== [https://halldweb1.jlab.org/talks/2012-1Q/Hall%20D%20Target%20Design%20Status,%20F...") |
|||
(7 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch, | + | Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch, James Brock, Josh Pierce, Josh Ballard |
− | == | + | ==Agenda== |
− | [ | + | *P&I Diagram [[Media:Latest Target P&I.pdf]] |
+ | *Dave's SOW [[Media:Target SOW.pdf]] | ||
+ | *Dave's Calcs [[Media:Target calcs1.pdf]] [[Media:Target calcs2.pdf]] | ||
+ | |||
+ | *controls | ||
+ | *Cost | ||
+ | *Schedule | ||
+ | *Who does what? | ||
==Notes== | ==Notes== | ||
− | * Target | + | * Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done. The latest P&I diagram was shown and discussed. The following are the results of the discussion; |
− | * | + | ** Target group has determined the components for the gas panel and will begin procurements and fabrication of all components associated with it. |
− | * Jim | + | ** The gas panel (fits in a 19" rack) will be attached to the Target installation cart |
− | ** | + | ** Target group will order the 500 gallon H2 tank for outside and take care of piping and instrumentation on the tank |
− | * | + | ** Jim Fochtman will layout the pad requirements for the tank and purge system and submit to facilities for installation. |
− | * | + | ** Jim to develop inside pipe routing |
− | * Jim will | + | ** Jim to look at inside purge tank location (needs to be away from ignition source) |
+ | **Josh to test lakeshore controller from target group Monday for compatability with Hall D controls | ||
+ | ** Jim to look at procuring chiller for refrig. compressor | ||
+ | ** Jim to get with Dave on scattering chamber design. | ||
+ | ** Tim to procure vacuum system pump cube (Pfeifer torbo cube)and gauging. | ||
+ | ** Chris to send out list of all items needed for monitoring/controlling from PLC system | ||
+ | ** Hall D people to discuss what needs to be shut off in hall when target vacuum goes south | ||
+ | ** Jim to develop H2 vent details | ||
+ | ** One target cell is made, will need to make one more | ||
+ | ** Dave to handle pressure system design as the DA | ||
+ | ** Look at heat shield next week | ||
+ | ** We will have bi-weekly mtgs | ||
+ | ** Cold head weight limit maxed out. |
Latest revision as of 16:47, 21 February 2013
Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch, James Brock, Josh Pierce, Josh Ballard
Agenda
- P&I Diagram Media:Latest Target P&I.pdf
- Dave's SOW Media:Target SOW.pdf
- Dave's Calcs Media:Target calcs1.pdf Media:Target calcs2.pdf
- controls
- Cost
- Schedule
- Who does what?
Notes
- Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done. The latest P&I diagram was shown and discussed. The following are the results of the discussion;
- Target group has determined the components for the gas panel and will begin procurements and fabrication of all components associated with it.
- The gas panel (fits in a 19" rack) will be attached to the Target installation cart
- Target group will order the 500 gallon H2 tank for outside and take care of piping and instrumentation on the tank
- Jim Fochtman will layout the pad requirements for the tank and purge system and submit to facilities for installation.
- Jim to develop inside pipe routing
- Jim to look at inside purge tank location (needs to be away from ignition source)
- Josh to test lakeshore controller from target group Monday for compatability with Hall D controls
- Jim to look at procuring chiller for refrig. compressor
- Jim to get with Dave on scattering chamber design.
- Tim to procure vacuum system pump cube (Pfeifer torbo cube)and gauging.
- Chris to send out list of all items needed for monitoring/controlling from PLC system
- Hall D people to discuss what needs to be shut off in hall when target vacuum goes south
- Jim to develop H2 vent details
- One target cell is made, will need to make one more
- Dave to handle pressure system design as the DA
- Look at heat shield next week
- We will have bi-weekly mtgs
- Cold head weight limit maxed out.