Difference between revisions of "GlueX TOF Meeting, December 5, 2013"

From GlueXWiki
Jump to: navigation, search
(Agenda)
m (Text replacement - "/halldweb1.jlab.org/" to "/halldweb.jlab.org/")
 
(One intermediate revision by the same user not shown)
Line 11: Line 11:
 
# Material procurement for support frame
 
# Material procurement for support frame
 
# Module installation plan
 
# Module installation plan
#* [https://halldweb1.jlab.org/talks/2013-4Q/D00000assy.pdf Chuck's installation document]
+
#* [https://halldweb.jlab.org/talks/2013-4Q/D00000assy.pdf Chuck's installation document]
 
#*([[Media:TOF BOM.pdf | TOF BOM]])
 
#*([[Media:TOF BOM.pdf | TOF BOM]])
 
# Testing results
 
# Testing results
Line 37: Line 37:
 
==Slides==
 
==Slides==
  
Talks can be deposited in the directory <code>/group/halld/www/halldweb1/html/talks/2013-4Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2013-4Q/ .
+
Talks can be deposited in the directory <code>/group/halld/www/halldweb/html/talks/2013-4Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2013-4Q/ .
  
 
=Minutes=
 
=Minutes=
Line 60: Line 60:
 
* Hussein will be coming to JLab to help with assembly.
 
* Hussein will be coming to JLab to help with assembly.
 
* Paul would like to come up and help start installation before the holiday break [this was before we heard about the C-channel delivery schedule.]
 
* Paul would like to come up and help start installation before the holiday break [this was before we heard about the C-channel delivery schedule.]
* Chuck is working on an updated [https://halldweb1.jlab.org/talks/2013-4Q/D00000assy.pdf installation document].
+
* Chuck is working on an updated [https://halldweb.jlab.org/talks/2013-4Q/D00000assy.pdf installation document].
 
* Tim suggested that we go though the current version of the document as a way to review the complete parts inventory. We did this, step-by-step, and we addressed most, if not all, of the parts issues.
 
* Tim suggested that we go though the current version of the document as a way to review the complete parts inventory. We did this, step-by-step, and we addressed most, if not all, of the parts issues.
  

Latest revision as of 14:25, 31 March 2015

GlueX Time-of-Flight Meeting
Thursday, December 5, 2013
10:00 am EST
JLab: CEBAF Center, F326/327

Agenda

  1. Announcements
  2. Review of meeting on November 7
  3. Delivery report
  4. Material procurement for support frame
  5. Module installation plan
  6. Testing results
  7. Contract close-out

Communication

Videoconference

  1. ESNet: 8542553

Desktop Sharing

  1. Go to http://esnet.readytalk.com
  2. In the "join a meeting" box enter the code: 1833622
  3. Fill in the participant registration form.

Telephone

To connect by telephone:

  1. dial:
  2. enter access code followed by the # sign: 1833622#

Slides

Talks can be deposited in the directory /group/halld/www/halldweb/html/talks/2013-4Q on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2013-4Q/ .

Minutes

Present:

  • FSU: Paul Eugenio, Sasha Ostrovidov
  • JLab: Eugene Chudakov, Chuck Hutton, Mark Ito (chair), Tim Whitlatch, Beni Zihlmann

Announcements

We congratulated the FSU team for completing delivery of all TOF modules to JLab. Well done!

Material procurement for support frame

  • Most of the pieces are in for the bench shield[?].
  • C-channels are due in next week. [Added in press: these are supposed to come in December 16.]
  • FSU has enough silicon foam rubber for the support frame. They will bring it up on the next trip.
  • Tim will call a meeting to make sure we have accounted for all of the parts and assign responsibility for providing them.

Module installation plan

  • Hussein will be coming to JLab to help with assembly.
  • Paul would like to come up and help start installation before the holiday break [this was before we heard about the C-channel delivery schedule.]
  • Chuck is working on an updated installation document.
  • Tim suggested that we go though the current version of the document as a way to review the complete parts inventory. We did this, step-by-step, and we addressed most, if not all, of the parts issues.

End of Construction Contract

  • FSU has an official end-of-contract in January. This may have to be extended.