* Minutes from previous meeting [[Controls_Meeting_2-Jun-2011|2-Jun-2011]] | * Minutes from previous meeting [[Controls_Meeting_2-Jun-2011|2-Jun-2011]] | ||
− | * Strategy for use of PLC vs IOC - Elliott | + | * Preliminary P&I diagram for FDC/CDC gas system [[Media:zihlmann_gassystem.pdf| Tracking Chamber Gas system]] - Beni |
− | ** | + | * Strategy for use of PLC vs IOC vs mixed system - Elliott |
− | ** CAN system | + | ** what criteria push us one way or the other? |
− | * [http:// | + | ** E.g: gas system, CAN system, FDC cooling, target, magnets, goniometer, HV/LV channels, crate control, etc. |
+ | * Update on Brooks 0254 control IOC and CSS/BOY evaluation - Hovanes | ||
+ | * [http://halldweb.jlab.org/mantisbt Mantis task tracker] - now being used for controls tasks | ||
* AOT | * AOT | ||
Line 23: | Line 25: | ||
==Next Meeting== | ==Next Meeting== | ||
− | + | ||
+ | Thurs 30-Jun-2011 CC F326 | ||
Line 29: | Line 32: | ||
=Minutes= | =Minutes= | ||
− | Attendees: Elliott W, Beni Z, | + | Attendees: Elliott W, Beni Z, Tim W, Josh B, Eugene C. |
+ | |||
+ | |||
+ | |||
+ | '''FDC Gas System''' | ||
+ | |||
+ | Beni presented a preliminary P&I diagram for the FDC/CDC gas systems. Much discussion ensued. | ||
+ | |||
+ | * < 15 psig, non-flammable gases allow us to avoid many ASME issues. Engineers need to sign off anything > 15 psig. | ||
+ | * methane may be used < 5%, non-flammable, pre-mix with another gas the best strategy. | ||
+ | * may need special vents if there's a way for the methane to collect. | ||
+ | * may bubble through alcohol - anti-aging, quencher. | ||
+ | * CDC uses 3 L/min, FDC 1 L/min nominal. | ||
+ | * will use embedded controls, probably will not need any control loops in PLC. |
Latest revision as of 18:44, 31 March 2015
Agenda
- Minutes from previous meeting 2-Jun-2011
- Preliminary P&I diagram for FDC/CDC gas system Tracking Chamber Gas system - Beni
- Strategy for use of PLC vs IOC vs mixed system - Elliott
- what criteria push us one way or the other?
- E.g: gas system, CAN system, FDC cooling, target, magnets, goniometer, HV/LV channels, crate control, etc.
- Update on Brooks 0254 control IOC and CSS/BOY evaluation - Hovanes
- Mantis task tracker - now being used for controls tasks
- AOT
Time/Location
9:30 AM Thurs 16-Jun-2011 CC F326
Announcements
Next Meeting
Thurs 30-Jun-2011 CC F326
Minutes
Attendees: Elliott W, Beni Z, Tim W, Josh B, Eugene C.
FDC Gas System
Beni presented a preliminary P&I diagram for the FDC/CDC gas systems. Much discussion ensued.
- < 15 psig, non-flammable gases allow us to avoid many ASME issues. Engineers need to sign off anything > 15 psig.
- methane may be used < 5%, non-flammable, pre-mix with another gas the best strategy.
- may need special vents if there's a way for the methane to collect.
- may bubble through alcohol - anti-aging, quencher.
- CDC uses 3 L/min, FDC 1 L/min nominal.
- will use embedded controls, probably will not need any control loops in PLC.