Coil Test Weekly Meeting 10-Jun-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 10-Jun-2010 9:30am ARC 428
Agenda
- F117 status - Tim, Elliott
- when must we vacate to make room for others? shortly after 16-Jul?
- is there enough room now for Fernando et al?
- currently hole in wall scheduled for 16-Jul
- B field - George, Floyd
- what is field at power supply?
- if too high, move it? field clamp?
- where to place controls racks (may not need RS485)?
- cannot handle high fields
- where to place computers?
- cannot handle high fields
- what is field at power supply?
- Safety review - Elliott
- 2-Jul meeting date
- 23-Jun deadline submit writing assignments to me (Elton thinks I'll need more time)
- 25-Jun submit documents to committee
- writing assignments (SME):
- George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W)
- Josh - ODH (Mat), cryo supply (Mat), cryo devices (Mat)
- Cody - magnet power (Bill Merz)
- Elliott - controls (Steve L)
- also need coil test plan from George and Josh, list of previous reviews
- Coil test plan - Josh
- Magnet power supply commissioning - Cody
- dump resistor
- magnetic field
- upgrade to higher current
- EPICS <--> PLC communications - Wesley
- Final A-B equipment order - Elliott
- Wiring and testing controls racks - Scot
- how much testing can be done in F117?
- how much needs the PLC?
- PLC programming status - Mark W
- C-glass calibrations - Elliott
- HMI and EWEB programming - Yi, Elliott
- 25 screen limit
- dual-monitors
- do we need a printer?
- do we need laptops?
- Installation status - George
- Coil repair status - George
- DOE mandated coil replacement plan status - George, Elliott