Coil Test Weekly Meeting 10-Jun-2010

From GlueXWiki
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 10-Jun-2010 9:30am ARC 428


Agenda

  • F117 status - Tim, Elliott
    • when must we vacate to make room for others? shortly after 16-Jul?
    • is there enough room now for Fernando et al?
    • note that hole in wall scheduled for 16-Jul
    • wiring should be done by 15-Jun, wire testing about a week later
    • how long does Mark W need test PLC program?
  • B field - George, Floyd
    • what is field at power supply?
      • if too high, move it? field clamp?
    • where to place controls racks (may not need RS485)?
      • cannot handle high fields
    • where to place computers?
      • cannot handle high fields
  • Safety review - Elliott
    • 2-Jul meeting date
    • 23-Jun deadline submit writing assignments to me (Elton thinks I'll need more time)
    • 25-Jun submit documents to committee
    • writing assignments (SME):
      • George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W)
      • Josh - ODH (Mat), cryo supply (Mat), cryo devices (Mat)
      • Cody - magnet power (Bill Merz)
      • Elliott - controls (Steve L)
    • also need coil test plan from George and Josh, list of previous reviews
  • Coil test plan - Josh
  • Magnet power supply commissioning - Cody
    • dump resistor
    • magnetic field
    • upgrade to higher current
  • EPICS <--> PLC communications - Wesley
  • Quick report from EPICS collaboration meeting - Wesley
  • Final equipment orders - Elliott
    • A-B components
    • relay cards (for open collector outputs)
    • anything else?
  • Wiring and testing controls racks - Scot
    • how much testing can be done in F117?
    • how much needs the PLC?
    • how to prepare for next coil to be tested?
    • who will update wiring diagrams?
  • PLC programming status - Mark W
    • C-glass calibrations - Elliott
  • HMI and EWEB programming - Yi, Elliott
    • 25 screen limit
    • dual-monitors
    • do we need a printer?
    • do we need laptops?
  • Installation status - George
  • Coil repair status - George
  • DOE mandated coil replacement plan status - George, Elliott