Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 10-Jun-2010 9:30am ARC 428
Agenda
- Safety review - Elliott
- 2-Jul meeting date
- 23-Jun deadline submit writing assignments to me
- 25-Jun submit documents to committee
- Coil test plan - George, Josh
- Update on safety interlock design - Mark S, Scot
- fast and slow dump circuits
- redundancy in power supply overcurrent interlock
- Magnet power supply commissioning - Cody
- dump resistor
- magnetic field
- upgrade to higher current
- Update on EPICS <--> PLC communications - Wesley
- Magnetic field near control racks and computers - George
- Final A-B equipment order - Elliott
- Wiring and testing controls racks - Scot
- how much testing can be done in F117?
- how much needs the PLC?
- PLC programming status - Mark W
- C-glass calibrations - George
- HMI and EWEB programming - Yi, Elliott
- 25 screen limit
- dual-monitors
- Installation status - George
- Coil repair status - George