JEF meeting, October 18, 2024

From GlueXWiki
Revision as of 08:40, 18 October 2024 by Somov (Talk | contribs)

Jump to: navigation, search

Connection

Meeting time and location:


Agenda

Preparation of parts for ECAL -- Sasha

  • - HV distribution boards [1][2]
- PCBs with 5 (12 x 4) and 5 (6 x 8) connectors are ready for two distribution boards. One more board will be ready during next week.
- Boxes for HV boards have been ordered. The lead time about 3 weeks.
- Communicated with Vince P. (JLab's machine shop) and Tim. Ordered 2 temporary distribution boards, if the delivery of the real ones is delayed

Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Installation of the light distribution board of the ECAL LMS [3]
- Fine-tune the light source. Slightly modified the design, ordered new LEDs
  • Implementing ECAL into the GlueX DAQ [4]
- rocecal3 crate was fixed [5] (initial DAQ implementation [6])
- implementing flash ADC scalers [7]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- implementing and verifying ECAL LMS trigger [9]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- Installation of scintillating paddles for cosmic tests [11]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- Connecting cooling pipes to the ECAL fan (done by tech group)
- Installing dark room ceiling and insulation inside the room, required for cooling test (almost complete)
- Test cooling system (in progress, almost complete)
- Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)

Restoring PS test setup [16] ECAL commissioning -- Sasha, All

  • Calibrations
  • Analysis/Simulation

Laveen Update