- Preparation of parts for ECAL -- Sasha
- - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
- - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
- - Fix front panel of two LV distribution boards [3]
- - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables
- - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
<! -- ** Report from students [4] -->
- - two remaining bundle of cables will be ready in about a week
- Installation and testing dividers has been completed [5]
- Installation of optical fibers [6]
- Detector installation page
- Safety briefings
- Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)