Agenda
- Preparation of parts for ECAL modules -- Sasha
- Module fabrication -- Sasha
- All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [3] - done
- Prepare to move modules into Hall D [4] [5]
- Tested, labeled, and bundled (53 bundlesout of 100) [6] of signal cables connected from the flash ADC to the patch panel [7]
- Removing signal cables from the FCAL and rearranging signal cables in the hall [8] Rearranging_FCAL_cables - done
- - 400 signal cables were removed,re-labeled and bundled
- - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
- - install two flash ADCs
- Cutting optical fibers and gluing plastic caps [9]
- Report from students
- Test fabricated modules using LMS [10]
- Testing of PMT dividers -- Sasha / Vlad
- All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Started installing detector modules [11]
- Detector installation page
- Updates from the meetings with Tim's group [12]
- Discussion of the FCAL2 installation procedures [13]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis
Minutes
Attendees: Sasha, Igal, Arshak, Zisis, Olga, Liping, Jane, Jon, Susan, S.T.
- Jane's group went to Shanghai and inspected 88 SICCAS crystals
- Found many poor quality crystals (several discolored, several with chips beyond surface level/chamfers)
- Will reject 23-25
- Will use remaining as spares or for other projects (not enough to instrument any more columns in insert)
- Long cables are arriving: have 1200 + 400 from FCAL
- 53/100 bundles have been prepared
- Remaining fibers for LMS still not expected until August/September
- All modules needed for insert have been fabricated, being prepared to move to hall D
- Testing each one using dark box (looking at waveforms on oscilloscope)
- Expect first article PMT dividers from outside company soon
- Stacking of lead glass modules in new frame has started, as of meeting 340 in place
- Up to layer 10, insert starts after layer 19, maybe middle of week of 7/17/23?
- Survey&alignment to check levelness before we get too far
- Arshak polishing fibers
- Liping visited Modern Physics Institute in China
- They are working on new accelerator facility to come online in 2025
- They plan to work on η physics, similar to REDTOP