JEF meeting, March 22, 2024
From GlueXWiki
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV short cables: received, checked, labeled (last week)
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 500 cables in total
- - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
- Ongoing projects -- Sasha / Vlad / Hakob / Laveen
- Testing of PMT dividers -- Sasha / Vlad / George
- - Testing procedure [6]
- - About 1420 dividers have been fabricated (Chris, Armen, Mindy)
- - Started removing power regulators on the newly fabricated dividers
- - George has tested 54 dividers (919 have been tested in total) [7].
- - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Preparing safety documents -- Sasha and Vlad
- The following ePASes have been submitted and approved: (1) Installation of the LMS, Installation of cables and dividers, Beam tests with the PS test setup, Preparing cables (EEL126), Fabrication of calorimeter prototypes (EEL126), Testing ECAL dividers (EEL118)
- Detector installation [8][9][10]
- Installation of the LMS
- Cable and divider installation [13][14][15]
- Power installation on the platform has been completed [16]
- Detector installation page
- Preparing safety documents -- Sasha and Vlad
- Analysis/Simulation