== Agenda == | == Agenda == | ||
* Discuss last weeks minutes https://halldweb1.jlab.org/wiki/index.php/May_28,_2013_Solenoid_Meeting | * Discuss last weeks minutes https://halldweb1.jlab.org/wiki/index.php/May_28,_2013_Solenoid_Meeting | ||
+ | * Work accomplished since last meeting | ||
+ | ** 15A test minus quench detector checks (magnet still resistive) | ||
+ | ** Preliminary 140A test procedure written [[Media:140A procedure rev C.pdf]] | ||
* Discuss path forward plan [[Media:wSchneider path forward.pdf]] | * Discuss path forward plan [[Media:wSchneider path forward.pdf]] | ||
** Probirs margin comparison [[Media:Margin comparison.pdf]] | ** Probirs margin comparison [[Media:Margin comparison.pdf]] | ||
** George's info [[Media:Quench plot zoom.png]]____ [[Media:Quench plot.png]] | ** George's info [[Media:Quench plot zoom.png]]____ [[Media:Quench plot.png]] | ||
* Plans for low current testing | * Plans for low current testing | ||
− | + | ||
** Power Supply ramp smoothing program | ** Power Supply ramp smoothing program | ||
** Power Supply resolution hardware fix (0-1.5 A/sec) | ** Power Supply resolution hardware fix (0-1.5 A/sec) |
Revision as of 13:33, 5 June 2013
Thursday June 6,2013 at 10am At Jefferson Lab, the meeting will be held in room ARC 231
Agenda
- Discuss last weeks minutes https://halldweb1.jlab.org/wiki/index.php/May_28,_2013_Solenoid_Meeting
- Work accomplished since last meeting
- 15A test minus quench detector checks (magnet still resistive)
- Preliminary 140A test procedure written Media:140A procedure rev C.pdf
- Discuss path forward plan Media:wSchneider path forward.pdf
- Probirs margin comparison Media:Margin comparison.pdf
- George's info Media:Quench plot zoom.png____ Media:Quench plot.png
- Plans for low current testing
- Power Supply ramp smoothing program
- Power Supply resolution hardware fix (0-1.5 A/sec)
- Voltage tap checks/fixes
- Short to ground location
- Power Supply hose replacement
- Plans for low current testing
- 15A Commissioning Plan Media:15A Plan.pdf
- 140A Commissioning plan
- Cool Down Plans
- Path Forward .......
Useful Info
- Documents available at M:\halld_engineering\Solenoid\Commissioning\Response to Quench