* Addition of Hall probe and fast readout correlated with magnet current | * Addition of Hall probe and fast readout correlated with magnet current | ||
** might detect turn-to-turn shorts | ** might detect turn-to-turn shorts | ||
+ | * Pager for coil test on-call person | ||
+ | ** n.b. we previously decided on a hand-off strategy | ||
* Installation status - all | * Installation status - all | ||
** vapor-cooled lead connections | ** vapor-cooled lead connections | ||
Line 24: | Line 26: | ||
*** Hall probe | *** Hall probe | ||
* OSP review and Conduct of Operations - Josh, George, Elliott | * OSP review and Conduct of Operations - Josh, George, Elliott | ||
− | ** | + | ** need to hand things in this week! |
+ | ** commissioning checklists | ||
+ | ** final versions of other docs, OSP cover page | ||
** what is left to do? | ** what is left to do? | ||
− | |||
* Do we need He vessel LHe level in interlock system - George, Elliott | * Do we need He vessel LHe level in interlock system - George, Elliott | ||
** backup to liquid level measurements? | ** backup to liquid level measurements? |
Revision as of 13:32, 6 October 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 7-Oct-2010 9:30am ARC 428
Agenda
- New coil test group members, mainly in consultant/oversight capacity
- Bill Schneider - superconducting magnet engineer
- Jonathan Creel - cryo and controls engineer
- Addition of Hall probe and fast readout correlated with magnet current
- might detect turn-to-turn shorts
- Pager for coil test on-call person
- n.b. we previously decided on a hand-off strategy
- Installation status - all
- vapor-cooled lead connections
- what's left?
- when do we give two weeks notice to Errol?
- Aftermath of DOE review 28-Sep - George, Elliott
- can we detect turn-to-turn shorts?
- pulse reflection in coil
- subcoil voltages
- Hall probe
- can we detect turn-to-turn shorts?
- OSP review and Conduct of Operations - Josh, George, Elliott
- need to hand things in this week!
- commissioning checklists
- final versions of other docs, OSP cover page
- what is left to do?
- Do we need He vessel LHe level in interlock system - George, Elliott
- backup to liquid level measurements?
- Test plan - Josh
- addition of check valve and relief valve in lead flow system
- Magnet power supply and interlock commissioning - Mark S
- latest status
- adding a shunt to the interlock system
- adding ground fault detection
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- guard shack
- what's left?
- backup PLC programmer, file locations, license key
- EPICS <--> PLC communications - Hovanes
- PV list from Jonathan Creel and PLC tags
- connection to guard shack
- under what circumstances do we notify the guard shack?
- HMI and EWEB programming - Yi, Hovanes
- current status
- tutorial?
- Coil repair status - George
- Solenoid review 25-26 Oct
- Preparations for testing next coil - George, Scot, Elliott
- hardware purchase/reuse strategy
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring