Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 7-Oct-2010 9:30am ARC 428


Agenda

  • New coil test group members, mainly in consultant/oversight capacity
    • Bill Schneider - superconducting magnet engineer
    • Jonathan Creel - cryo and controls engineer
  • OSP docs and writing assignments - all
    • Note: MUST get everything to committee immediately to get OSP by 18-Oct!!!
    • writing assignments
    • will need RadCon survey, may need TLD to work on platform
  • Addition of Hall probe and fast readout correlated with magnet current
    • to detect turn-to-turn shorts
    • needs rigid mount, but no personnel access to magnet bore when cold
  • Pager for coil test on-call person
    • n.b. we previously decided on a hand-off strategy
    • the new ones are free!
  • Installation status - all
    • vapor-cooled lead connections
    • what's left?
    • when do we give two weeks notice to Errol?
  • Aftermath of DOE review 28-Sep - George, Elliott
    • can we detect turn-to-turn shorts?
      • pulse reflection in coil
      • subcoil voltages
      • Hall probe
  • Do we need He vessel LHe level in interlock system - George, Elliott
    • backup to liquid level measurements?
  • Narrative/Test Plan - Josh
    • addition of check valve and relief valve in lead flow system
    • phased cooldown of LN2 shields
    • any other changes?
  • Magnet power supply and interlock commissioning - Mark S
    • latest status
    • adding a shunt to the interlock system
    • adding ground fault detection
  • Controls racks - Scot
    • strain gauge interlock
    • UPS interlock
    • anything else?
  • PLC programming/testing status - Mark W
    • UPS interlock
    • guard shack
    • what's left?
    • backup PLC programmer, file locations, license key
  • EPICS <--> PLC communications - Hovanes
    • PV list from Jonathan and PLC tags
    • connection to guard shack
    • under what circumstances do we notify the guard shack?
  • HMI and EWEB programming - Yi, Hovanes
    • current status
    • tutorial?
  • Coil repair status - George
  • Solenoid review 25-26 Oct
  • Preparations for testing next coil - George, Scot, Elliott
    • hardware purchase/reuse strategy
    • update P&I
    • splices
    • yoke location
    • piping adaptors
    • downstream yoke spacers
    • controls racks rewiring