Difference between revisions of "Coil Test Weekly Meeting 15-Jul-2010"
From GlueXWiki
m |
m |
||
Line 18: | Line 18: | ||
** Can magnet power be on unattended? | ** Can magnet power be on unattended? | ||
* Magnet power supply and interlock commissioning - Cody | * Magnet power supply and interlock commissioning - Cody | ||
− | ** dump resistor, flow switches, interlocks, etc. | + | ** dump resistor, insulation of dump resistor, flow switches, interlocks, etc. |
** RS232 connection to power supply | ** RS232 connection to power supply | ||
** crash buttons - fast or slow dump? | ** crash buttons - fast or slow dump? |
Latest revision as of 16:20, 14 July 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 15-Jul-2010 9:30am ARC 428
Agenda
- Training requirements - ODH, ladder, others?
- Printer - Elliott
- F117 - Scot, Elliott, Mark S, Tom
- schedule for hole in the wall, door, when will we move out?
- Safety review aftermath - Elliott
- OSP is the next step
- Coil test plan - Josh
- Can magnet power be on unattended?
- Magnet power supply and interlock commissioning - Cody
- dump resistor, insulation of dump resistor, flow switches, interlocks, etc.
- RS232 connection to power supply
- crash buttons - fast or slow dump?
- polarity and polarity reversal lockout
- lock door when magnet ramping down but power supply turned off?
- interlock on strain gauges?
- B field - Elliott
- where to place computers?
- Controls racks - Scot, Elliott
- what else is left to do?
- Ethernet in racks, new hub
- C-glass sensor locations?
- PLC programming/testing status - Mark W
- UPS status - Mark W, Elliott
- relay modules, use in interlock system
- connection to PLC?
- EPICS <--> PLC communications - Wesley, Elliott
- connection to guard shack
- HMI and EWEB programming - Yi, Elliott
- Installation status - George, Mark S
- cryo can delivery
- Two weeks notice to Errol
- backup power in Test Lab
- Coil repair status - George
- DOE mandated coil replacement plan status - George, Elliott