Difference between revisions of "JEF meeting, December 13, 2024"

From GlueXWiki
Jump to: navigation, search
(Agenda)
 
Line 60: Line 60:
 
:: -[https://halldweb.jlab.org/detectors/fcal2/installation/meetings/12_06_2024 Adjusting HVs]
 
:: -[https://halldweb.jlab.org/detectors/fcal2/installation/meetings/12_06_2024 Adjusting HVs]
 
'''Analysis/Simulation'''
 
'''Analysis/Simulation'''
 +
 +
=Minutes=
 +
Attendees: Bill, Igal, Sasha, Vlad, Zhikun, Laveen, Phil, Jane, Axel, S.T.
 +
* 2 HV distribution boards installed on south side, cabling continues
 +
** Fixed several issues on south bottom
 +
*** Broken connector, holes too small, broken clips
 +
*** Similar problems seen on south top, also cable swaps and disconnected dividers
 +
** South top cabling finished over weekend, scalers look good
 +
* Temporary HV boards on north side removed, find HV boards for north bottom installed over weekend, waiting for final boards for north top
 +
* LV problem for North top fixed (was drawing 4 Amps)
 +
** Consider lower trip setting for LV?
 +
* 3D printing for reference PMT (for LMS) setup sarted
 +
* Chris S. working on final layout for LMS light source (with 25 LEDs), to order the week of 9/16/24, receive next year?
 +
* Temperature sensors arrived and have been installed
 +
* 2 new fans have been installed
 +
** Need to be put into interlock

Latest revision as of 09:54, 16 December 2024

Connection

Meeting time and location:


Agenda

Preparation of parts for ECAL -- Sasha

-Four boxes for HV distribution boards have arrived to the lab. PCBs with HV connectors were installed on 2 distribution boards [1][2]
-Updated design of the LMS light source with 25 LEDS. PCB layout under preparation, expect to order the new PCB during next week.
-Four temperature sensors (RTD) arrived to the lab. They will be installed in the ECAL divider region during next week.
-Two additional fans for cooling the ECAL dividers arrived. Will be installed today.

-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [3]
- rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- implementing flash ADC scalers [6][7]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- implementing and verifying ECAL LMS trigger [9]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- New version of DAQ, VTP included as a DAQ component [11]
  • Installation of scintillating paddles for cosmic tests [12] [13][14]
  • ECAL HV interlock check [15]
  • Cable map of the ECAL LG modules after installing ECAL [16]
  • Reinstalling cables on the ECAL LV distribution board [17]
  • Safety briefings - Vlad, Sasha
  • Detector installation page
  • Commissioning north part of the ECAL (instrumented with 2 temporary HV distribution boards) [18][19][20][21]
  • Commissioning of the south bottom region [22]
  • Commissioning of the south top region [23]
  • Fix LV issues (north top region) [24]
  • First cosmic event in the ECAL [25]
  • Temperature scan in the ECAL divider region [26][27][28][29]
Meeting with Tim, additional fans will be installed
  • Repairing a few ECAL LMS optical fibers [30][31]
  • Preparing for the installation of the insulation on the detector face
- Removing Tedlar from the face of the detector [32]
- ECAL flash ADC scalers before removing detector face cover [33]
  • Preparing for the run -- Sasha
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- Installing additional fans (will be installed today)
- Installing insulation on the detector's face (done)

Restoring PS test setup [34]

ECAL commissioning -- Sasha, All

Laveen update[[35]]

Calibrations

-First look on cosmic data -- Zhikun
-Adjusting HVs

Analysis/Simulation

Minutes

Attendees: Bill, Igal, Sasha, Vlad, Zhikun, Laveen, Phil, Jane, Axel, S.T.

  • 2 HV distribution boards installed on south side, cabling continues
    • Fixed several issues on south bottom
      • Broken connector, holes too small, broken clips
      • Similar problems seen on south top, also cable swaps and disconnected dividers
    • South top cabling finished over weekend, scalers look good
  • Temporary HV boards on north side removed, find HV boards for north bottom installed over weekend, waiting for final boards for north top
  • LV problem for North top fixed (was drawing 4 Amps)
    • Consider lower trip setting for LV?
  • 3D printing for reference PMT (for LMS) setup sarted
  • Chris S. working on final layout for LMS light source (with 25 LEDs), to order the week of 9/16/24, receive next year?
  • Temperature sensors arrived and have been installed
  • 2 new fans have been installed
    • Need to be put into interlock