+ | Attendees: Bill, Igal, Sasha, Vlad, Zhikun, Laveen, Phil, Jane, Axel, S.T. | ||
+ | * 2 HV distribution boards installed on south side, cabling continues | ||
+ | ** Fixed several issues on south bottom | ||
+ | *** Broken connector, holes too small, broken clips | ||
+ | *** Similar problems seen on south top, also cable swaps and disconnected dividers | ||
+ | ** South top cabling finished over weekend, scalers look good | ||
+ | * Temporary HV boards on north side removed, find HV boards for north bottom installed over weekend, waiting for final boards for north top | ||
+ | * LV problem for North top fixed (was drawing 4 Amps) | ||
+ | ** Consider lower trip setting for LV? | ||
+ | * 3D printing for reference PMT (for LMS) setup sarted | ||
+ | * Chris S. working on final layout for LMS light source (with 25 LEDs), to order the week of 9/16/24, receive next year? | ||
+ | * Temperature sensors arrived and have been installed | ||
+ | * 2 new fans have been installed | ||
+ | ** Need to be put into interlock |
Latest revision as of 09:54, 16 December 2024
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- -Four boxes for HV distribution boards have arrived to the lab. PCBs with HV connectors were installed on 2 distribution boards [1][2]
- -Updated design of the LMS light source with 25 LEDS. PCB layout under preparation, expect to order the new PCB during next week.
- -Four temperature sensors (RTD) arrived to the lab. They will be installed in the ECAL divider region during next week.
- -Two additional fans for cooling the ECAL dividers arrived. Will be installed today.
-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Implementing ECAL into the GlueX DAQ [3]
- - rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- - implementing flash ADC scalers [6][7]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- - implementing and verifying ECAL LMS trigger [9]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- - Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- - New version of DAQ, VTP included as a DAQ component [11]
- Installation of scintillating paddles for cosmic tests [12] [13][14]
- ECAL HV interlock check [15]
- Cable map of the ECAL LG modules after installing ECAL [16]
- Reinstalling cables on the ECAL LV distribution board [17]
- Safety briefings - Vlad, Sasha
- Detector installation page
- Commissioning north part of the ECAL (instrumented with 2 temporary HV distribution boards) [18][19][20][21]
- Commissioning of the south bottom region [22]
- Commissioning of the south top region [23]
- Fix LV issues (north top region) [24]
- First cosmic event in the ECAL [25]
- Temperature scan in the ECAL divider region [26][27][28][29]
- Meeting with Tim, additional fans will be installed
- Repairing a few ECAL LMS optical fibers [30][31]
- Preparing for the installation of the insulation on the detector face
- Preparing for the run -- Sasha
- Page for shift Takers
- ECAL in the Experimental Safety Assessment Document (ESAD)
- EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Installing additional fans (will be installed today)
- - Installing insulation on the detector's face (done)
Restoring PS test setup [34]
ECAL commissioning -- Sasha, All
Laveen update[[35]]
Calibrations
Analysis/Simulation
Minutes
Attendees: Bill, Igal, Sasha, Vlad, Zhikun, Laveen, Phil, Jane, Axel, S.T.
- 2 HV distribution boards installed on south side, cabling continues
- Fixed several issues on south bottom
- Broken connector, holes too small, broken clips
- Similar problems seen on south top, also cable swaps and disconnected dividers
- South top cabling finished over weekend, scalers look good
- Fixed several issues on south bottom
- Temporary HV boards on north side removed, find HV boards for north bottom installed over weekend, waiting for final boards for north top
- LV problem for North top fixed (was drawing 4 Amps)
- Consider lower trip setting for LV?
- 3D printing for reference PMT (for LMS) setup sarted
- Chris S. working on final layout for LMS light source (with 25 LEDs), to order the week of 9/16/24, receive next year?
- Temperature sensors arrived and have been installed
- 2 new fans have been installed
- Need to be put into interlock