Difference between revisions of "JEF meeting, February 16, 2024"
From GlueXWiki
(→Agenda) |
|||
Line 26: | Line 26: | ||
** - ePASS submitted and approved | ** - ePASS submitted and approved | ||
** - George from the DSG continued testing dividers | ** - George from the DSG continued testing dividers | ||
− | ** - Have tested 637 + | + | ** - Have tested 637 + 134 = 771 dividers (about 100 available for testing) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. |
** - Spare PMTs, have about 20, likely need more for the future (order 30 more )? | ** - Spare PMTs, have about 20, likely need more for the future (order 30 more )? | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad |
Revision as of 10:11, 16 February 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 cables 1445 in total
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 250 cables in total
- - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables, 100 short LV cables tested and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Radiation tests of the PMT active base [5]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / George
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
- Detector installation [8][9][10]
- Installation of the LMS
- 175 fibers installed during this week (313 in total) [11] https://logbooks.jlab.org/entry/4249236]
- Cable and divider installation [12]
- Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
- Detector installation page