Difference between revisions of "JEF meeting, February 2, 2024"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 33: | Line 33: | ||
*** 143 fibers installed during this week (some delays with trainings and safety docs) [https://logbooks.jlab.org/entry/4246934] [https://logbooks.jlab.org/entry/4243052] | *** 143 fibers installed during this week (some delays with trainings and safety docs) [https://logbooks.jlab.org/entry/4246934] [https://logbooks.jlab.org/entry/4243052] | ||
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas) | *** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas) | ||
− | ** Cable and divider installation | + | ** Cable and divider installation [https://logbooks.jlab.org/entry/4245946] |
− | + | *** Bundled and installed signal, HV, and LV cables on the first layer | |
** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ) | ** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ) | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] |
Revision as of 10:19, 2 February 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 1280 in total
- - HV distribution boards: in preparation
- - LV cables: 150 cables received
- - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables, 100 short LV cables tested and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Preparation of the LMS
- - Need to glue Al flange to the optical fiber
- - Ready for installation [5]
- - Radiation tests of the PMT active base [6]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [9][10][11]
- Installation of the LMS
- Cable and divider installation [14]
- Bundled and installed signal, HV, and LV cables on the first layer
- Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
- Detector installation page