Difference between revisions of "JEF meeting, December 1, 2023"
From GlueXWiki
(→Agenda) |
|||
Line 6: | Line 6: | ||
=Agenda= | =Agenda= | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
− | ** - signal cables: | + | ** - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready. |
** - signal patch panels are ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] | ** - signal patch panels are ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] | ||
− | ** - HV cables: have received | + | ** - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production |
** - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon. | ** - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon. | ||
** - LV cables: ordered, lead time unclear | ** - LV cables: ordered, lead time unclear | ||
− | ** - LV distribution boards. The design of the LV distribution board has been finalized | + | ** - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week. |
** - Optical fibers: received all | ** - Optical fibers: received all | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all |
Revision as of 10:13, 1 December 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
- - signal patch panels are ready [1]
- - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
- - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
- - LV cables: ordered, lead time unclear
- - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- - Testing and labeling cables (Recently labeled cables in boxes)[2]
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
- Wrapped crystals - done
- Parts for TAC[4] - done
- Modules for prototype (25 are ready) - done
- - Preparation of the LMS [5]
- - 3-D print and machine mounting plate (coupling to the integrating sphere]
- - 3-D print support structure for gluing fibers to the mounting plate [Boby]
- - Machined Al plate for fiber polishing
- - Installing fibers; will start gluing soon [6][7]
- - The LMS should be ready for the installation on the detector during next week.
- - Install labels on the detector [8]
- - Installation of the trigger and readout electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
- Analysis/Simulation
- Added new JEF simulation page to wiki
- Rate simulation studies