Line 13: | Line 13: | ||
** - Optical fibers: received all | ** - Optical fibers: received all | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
− | ** - Tested and labeled | + | ** - Tested and labeled 240 short signal cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)] |
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ] | ** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ] | ||
::: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] | ::: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] | ||
::: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] | ::: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] | ||
+ | ::: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg Modules for prototype] | ||
** - Polished about 80 fiber plastic caps | ** - Polished about 80 fiber plastic caps | ||
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] |
Revision as of 09:20, 20 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: all cables are ready. 240 have been labeled during this week.
- - signal patch panels are ready [1]
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: check HV distribution boards during this week. Chris is finalizing design of the distribution board, should order 4 boards soon.
- - LV cables: ordered, lead time unclear
- - LV distribution boards: met with Chris and Stephanie on Monday last week. The design of the LV distribution board has been fixed.
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- - Tested and labeled 240 short signal cables (Recently labeled cables in boxes)
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [2]
- - Polished about 80 fiber plastic caps
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Plastic caps have been glued to all fibers
- Returning low-quality crystals to SICCAS -- Sasha
- 11 crystals were wrapped and placed into the box; they are ready for shipment to SICCAS [13]
- Analysis/Simulation
- First look at impact of GEMTRD -- Simon