Difference between revisions of "JEF meeting, August 11, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 22: | Line 22: | ||
** Work on refurbishing LG modules (wrapping, PMTs, etc.) | ** Work on refurbishing LG modules (wrapping, PMTs, etc.) | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
− | ** Received 10 dividers (first article), going to test them during this week (Chris) | + | ** Received 10 dividers (first article) ! , going to test them during this week (Chris) |
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob |
Revision as of 08:58, 11 August 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - 70 SICCAS crystals were shipped to us
- Received 900 short signal cables [1]
- Procurement parts for the LMS:
- - Waiting for 7,600 ft of optical fibers (August/September)
- Crystals:
- Module fabrication -- Sasha
- All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2] - done
- Prepare to move modules into Hall D [3] [4][5], wrap modules with sort towels.Moved about 800 crystals to the hall [6].
- Tested, labeled, and bundled all 100 (+ 2 spares) [7] signal cables connected from the flash ADC to the patch panel [8]. Receive cartridges for the printer, will resume labeling and cable bundling today.
- Cutting optical fibers and gluing plastic caps [9], waiting for 7600 ft of optical fibers
- Report from students
- Test fabricated modules using LMS [10], 1242 modules have been tested (need to update the wiki page)
- Work on refurbishing LG modules (wrapping, PMTs, etc.)
- Testing of PMT dividers -- Sasha / Vlad
- Received 10 dividers (first article) ! , going to test them during this week (Chris)
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation [11][12][13]
- Detector installation page
- Updates from the meetings with Tim's group [14]
- Discussion of the FCAL2 installation procedures [15]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Analysis/Simulation
- Island algorithm update--Simon