Difference between revisions of "JEF meeting, January 20, 2023"
From GlueXWiki
m |
|||
Line 6: | Line 6: | ||
*'''Preparation of parts for FCAL2 modules''' -- Sasha | *'''Preparation of parts for FCAL2 modules''' -- Sasha | ||
− | * '''Module fabrication''' -- Sasha** Install | + | ** Received all 150 CRYTUR crystals from physics division (22-C0275) [https://halldweb.jlab.org/wiki/index.php/CRYTUR ] |
+ | *** Expect to receive 95 more CRYTUR crystals in May (835 + 95 = 930 in total) | ||
+ | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 835 (ALL available CRYTUR) ] | ||
+ | *** 10 crystals wrapped since last meeting | ||
+ | *** Available for wrapping: 10 CRYTUR crystals, 140 SICCAS crystals from CCAL | ||
+ | *** Mindy (DSG group) continues wrapping crystals and soldering wires to sockets | ||
+ | ** Disassembling CCAL | ||
+ | *** CCAL moved to the ESB | ||
+ | *** [[All modules (with SICCAS crystals) are removed]] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] | ||
+ | * '''Module fabrication''' -- Sasha | ||
+ | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
+ | ** Fabricated modules: <span style="color:#FF0000"> Total 1408 </span> (12 modules fabricated since last week) | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS] | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 832 CRYTUR], available: 3 | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)] | ||
+ | * '''[[Testing of PMT dividers]]''' -- Sasha / Arshak | ||
+ | ** All parts for dividers have been ordered | ||
+ | ** Install 25 modules with new dividers on the CCAL, build prototype of LV patch pannel (check rate and noise) | ||
* '''Installation of the FCAL2 detector''' -- Sasha / Arshak | * '''Installation of the FCAL2 detector''' -- Sasha / Arshak | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_16,_2022_FCAL_Insert_Installation_Meeting] | ||
+ | ** Manpower and division of tasks | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ||
+ | ** Meeting with the detector imaging group | ||
* '''Light Monitoring System''' -- Arshak | * '''Light Monitoring System''' -- Arshak | ||
+ | **[https://userweb.jlab.org/~aasatury/Fcal_LMS/beam_test2/ Beam test] | ||
* '''Simulations/Analysis''' | * '''Simulations/Analysis''' | ||
* '''Talk on JEF at GHP conference''' | * '''Talk on JEF at GHP conference''' |
Revision as of 09:48, 20 January 2023
eeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Received all 150 CRYTUR crystals from physics division (22-C0275) [1]
- Expect to receive 95 more CRYTUR crystals in May (835 + 95 = 930 in total)
- Wrapped CRYTUR crystals: 835 (ALL available CRYTUR)
- 10 crystals wrapped since last meeting
- Available for wrapping: 10 CRYTUR crystals, 140 SICCAS crystals from CCAL
- Mindy (DSG group) continues wrapping crystals and soldering wires to sockets
- Disassembling CCAL
- CCAL moved to the ESB
- All modules (with SICCAS crystals) are removed
- List of available parts
- Received all 150 CRYTUR crystals from physics division (22-C0275) [1]
- Module fabrication -- Sasha
- Fabricated modules: Total 1408 (12 modules fabricated since last week)
- Testing of PMT dividers -- Sasha / Arshak
- All parts for dividers have been ordered
- Install 25 modules with new dividers on the CCAL, build prototype of LV patch pannel (check rate and noise)
- Installation of the FCAL2 detector -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [2]
- Manpower and division of tasks
- Projects for summer students
- Meeting with the detector imaging group
- Light Monitoring System -- Arshak
- Simulations/Analysis
- Talk on JEF at GHP conference