* Simulations/Analysis | * Simulations/Analysis | ||
+ | * Preparation of parts for FCAL2 modules -- Sasha | ||
** Received 40 CRYTUR crystals from Physics Division[https://halldweb.jlab.org/wiki-private/index.php/PMT_for_FCAL_insert] | ** Received 40 CRYTUR crystals from Physics Division[https://halldweb.jlab.org/wiki-private/index.php/PMT_for_FCAL_insert] | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 717 (10 since last week) ] | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 717 (10 since last week) ] |
Revision as of 09:36, 7 October 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 40 CRYTUR crystals from Physics Division[1]
- Wrapped CRYTUR crystals: 717 (10 since last week)
- Available for wrapping: 762 - 717 = 45
- DSG group continues wrapping
- List of available parts
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1291 (44 modules fabricated since last week)
- All SICCAS 576 SICCAS
- 715 CRYTUR, available: 47
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Preparation of parts for FCAL2 modules -- Sasha
- Light Monitoring System -- Arshak