** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] | ||
* Module fabrication -- Sasha | * Module fabrication -- Sasha | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] | ||
+ | ** Fabricated modules: <span style="color:#FF0000"> Total 1247 </span> (25 modules fabricated since last week) | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS] | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 671 CRYTUR], available: 51 | ||
+ | * Updates from the FCAL installation meetings with Tim's group -- Sasha | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/August_10,_2022_FCAL_Insert_Installation_Meeting Meeting in August 10] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings Link to the earlier design meetings] | ||
+ | |||
* Updates from the FCAL installation meetings with Tim's group -- Sasha | * Updates from the FCAL installation meetings with Tim's group -- Sasha | ||
* Light Monitoring System -- Arshak | * Light Monitoring System -- Arshak |
Revision as of 10:48, 30 September 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 100 PMTs (the last batch) [1]
- All PMTs have been checked (measured diameter)
- 39 PMTs were exchanged with the NPS (they are slightly tight)
- Wrapped CRYTUR crystals: 707 (15 since last week)
- Available for wrapping: 722 - 707 = 15
- DSG group continues wrapping
- List of available parts
- Received 100 PMTs (the last batch) [1]
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1247 (25 modules fabricated since last week)
- All SICCAS 576 SICCAS
- 671 CRYTUR, available: 51
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak