Difference between revisions of "February 25, 2021 CPP Design Meeting/ERR discussion"
From GlueXWiki
(Created page with "== Meeting Time and Place == Thursday Feb 18, 2021, 2pm Bluejeans https://bluejeans.com/465620466 * Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon == Agen...") |
(→Agenda) |
||
Line 6: | Line 6: | ||
== Agenda == | == Agenda == | ||
− | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/ | + | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/February_18,_2021_CPP_Design_Meeting/ERR_discussion |
− | * Readiness Review | + | * Readiness Review Report |
− | ** | + | ** [[Media:CPP_ERR_Report.pdf]] |
** [[CPP and NPP Readiness Review]] | ** [[CPP and NPP Readiness Review]] | ||
* Schedule with Resources [[Media:CPP_Schedule_Resources_v2.pdf]] | * Schedule with Resources [[Media:CPP_Schedule_Resources_v2.pdf]] |
Revision as of 13:52, 25 February 2021
Meeting Time and Place
Thursday Feb 18, 2021, 2pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/February_18,_2021_CPP_Design_Meeting/ERR_discussion
- Readiness Review Report
- Schedule with Resources Media:CPP_Schedule_Resources_v2.pdf
- Solid Pb target support and installation Media:CPP_Target_pic.pdf
- Target change out concept Media:CPP_Target_Mech_concept.jpg
- Gluex Commissioning Target support stand Media:CPP_Target_Solid_support.jpg
- Microscope move?
- Gas system Bubblers - Beni has some
- Design/Procurement status
- Things to work out
- Gas line manifold/bubblers
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Documentation for ERR
- Microscope move