Difference between revisions of "Run Planning Meeting Notes, September 10 - 16, 2020"
From GlueXWiki
(→Thursday, September 10 at 8:45) |
(→Thursday, September 10 at 8:45) |
||
Line 20: | Line 20: | ||
#*[https://logbooks.jlab.org/entry/3844610 New PWO crystals installed] | #*[https://logbooks.jlab.org/entry/3844610 New PWO crystals installed] | ||
#*[https://logbooks.jlab.org/entry/3844871 Waiting for CCAL] | #*[https://logbooks.jlab.org/entry/3844871 Waiting for CCAL] | ||
− | |||
# Run plan | # Run plan | ||
Line 28: | Line 27: | ||
#* Special tasks remaining: | #* Special tasks remaining: | ||
#**Beam rastering test | #**Beam rastering test | ||
− | #** | + | #**Periodic harp Scans (last one done on [https://logbooks.jlab.org/entry/3841546 Sept. 5th]). The rates and transmission [https://logbooks.jlab.org/entry/3845189 have been stable] |
#**Empty target run? | #**Empty target run? |
Revision as of 07:32, 10 September 2020
<- Back to Run Coordination Meetings:Summer2020
MEDCON 5 restrictions (Bob May email)
- adhere to counting room capacity restrictions
- maintain 6 ft. separation (briefly passing another person inside 6 ft. while moving about the counting room is inevitable and is OK)
- wear masks anytime more than one person present in the counting room
- at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.
- food and drink consumption - because it requires removing face coverings to consume - should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.
Thursday, September 10 at 8:45
- Last 24 hours:
- Reports/issues:
- Run plan
- Continue production runs
- Tuesday Sept. 15th: 3h of beam study expected
- Thursday or Friday Sept. 17th/18th: Hall C pass change from 5 to 1 pass
- Special tasks remaining:
- Beam rastering test
- Periodic harp Scans (last one done on Sept. 5th). The rates and transmission have been stable
- Empty target run?