Difference between revisions of "Coil Test Weekly Meeting 15-Jul-2010"
From GlueXWiki
m |
m |
||
Line 9: | Line 9: | ||
'''Agenda''' | '''Agenda''' | ||
− | * | + | * Training requirements - ODH, ladder, others? |
+ | * Printer - Elliott | ||
+ | * F117 - Scot, Elliott, Mark S, Tom | ||
** schedule for hole in the wall, door, when will we move out? | ** schedule for hole in the wall, door, when will we move out? | ||
− | * Safety review - Elliott | + | * Safety review aftermath - Elliott |
+ | ** OSP is the next step | ||
* Coil test plan - Josh | * Coil test plan - Josh | ||
− | * Magnet power supply commissioning - Cody | + | ** Can magnet power be on unattended? |
− | ** dump resistor | + | * Magnet power supply and interlock commissioning - Cody |
− | * | + | ** dump resistor, flow switches, interlocks, etc. |
− | ** | + | ** RS232 connection to power supply |
− | ** where to | + | ** crash buttons - fast or slow dump? |
− | * Controls racks - Scot, | + | ** polarity and polarity reversal lockout |
− | + | ** lock door when magnet ramping down but power supply turned off? | |
+ | ** interlock on strain gauges? | ||
+ | * B field - Elliott | ||
+ | ** where to place computers? | ||
+ | * Controls racks - Scot, Elliott | ||
** what else is left to do? | ** what else is left to do? | ||
+ | ** Ethernet in racks, new hub | ||
+ | ** C-glass sensor locations? | ||
* PLC programming/testing status - Mark W | * PLC programming/testing status - Mark W | ||
− | * | + | * UPS status - Mark W, Elliott |
− | * EPICS <--> PLC communications - Wesley | + | ** relay modules, use in interlock system |
+ | ** connection to PLC? | ||
+ | * EPICS <--> PLC communications - Wesley, Elliott | ||
+ | ** connection to guard shack | ||
* HMI and EWEB programming - Yi, Elliott | * HMI and EWEB programming - Yi, Elliott | ||
− | * Installation status - George | + | * Installation status - George, Mark S |
+ | ** cryo can delivery | ||
+ | ** Two weeks notice to Errol | ||
+ | ** backup power in Test Lab | ||
* Coil repair status - George | * Coil repair status - George | ||
* DOE mandated coil replacement plan status - George, Elliott | * DOE mandated coil replacement plan status - George, Elliott |
Revision as of 15:40, 14 July 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 15-Jul-2010 9:30am ARC 428
Agenda
- Training requirements - ODH, ladder, others?
- Printer - Elliott
- F117 - Scot, Elliott, Mark S, Tom
- schedule for hole in the wall, door, when will we move out?
- Safety review aftermath - Elliott
- OSP is the next step
- Coil test plan - Josh
- Can magnet power be on unattended?
- Magnet power supply and interlock commissioning - Cody
- dump resistor, flow switches, interlocks, etc.
- RS232 connection to power supply
- crash buttons - fast or slow dump?
- polarity and polarity reversal lockout
- lock door when magnet ramping down but power supply turned off?
- interlock on strain gauges?
- B field - Elliott
- where to place computers?
- Controls racks - Scot, Elliott
- what else is left to do?
- Ethernet in racks, new hub
- C-glass sensor locations?
- PLC programming/testing status - Mark W
- UPS status - Mark W, Elliott
- relay modules, use in interlock system
- connection to PLC?
- EPICS <--> PLC communications - Wesley, Elliott
- connection to guard shack
- HMI and EWEB programming - Yi, Elliott
- Installation status - George, Mark S
- cryo can delivery
- Two weeks notice to Errol
- backup power in Test Lab
- Coil repair status - George
- DOE mandated coil replacement plan status - George, Elliott