Difference between revisions of "Coil Test Weekly Meeting 10-Jun-2010"
From GlueXWiki
m |
|||
Line 8: | Line 8: | ||
'''Agenda''' | '''Agenda''' | ||
+ | |||
+ | * B field - George, Floyd | ||
+ | ** what is field at power supply? | ||
+ | ** where to place controls racks? | ||
* Safety review - Elliott | * Safety review - Elliott | ||
Line 13: | Line 17: | ||
** 23-Jun deadline submit writing assignments to me | ** 23-Jun deadline submit writing assignments to me | ||
** 25-Jun submit documents to committee | ** 25-Jun submit documents to committee | ||
− | * | + | ** everyone must start writing assignments |
− | * | + | ** also need coil test plan |
− | ** | + | |
− | + | ||
* Magnet power supply commissioning - Cody | * Magnet power supply commissioning - Cody | ||
** dump resistor | ** dump resistor | ||
** magnetic field | ** magnetic field | ||
** upgrade to higher current | ** upgrade to higher current | ||
− | * | + | * EPICS <--> PLC communications - Wesley |
− | + | ||
* Final A-B equipment order - Elliott | * Final A-B equipment order - Elliott | ||
* Wiring and testing controls racks - Scot | * Wiring and testing controls racks - Scot | ||
Line 28: | Line 29: | ||
** how much needs the PLC? | ** how much needs the PLC? | ||
* PLC programming status - Mark W | * PLC programming status - Mark W | ||
− | ** C-glass calibrations - | + | ** C-glass calibrations - Elliott |
* HMI and EWEB programming - Yi, Elliott | * HMI and EWEB programming - Yi, Elliott | ||
** 25 screen limit | ** 25 screen limit |
Revision as of 14:33, 7 June 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 10-Jun-2010 9:30am ARC 428
Agenda
- B field - George, Floyd
- what is field at power supply?
- where to place controls racks?
- Safety review - Elliott
- 2-Jul meeting date
- 23-Jun deadline submit writing assignments to me
- 25-Jun submit documents to committee
- everyone must start writing assignments
- also need coil test plan
- Magnet power supply commissioning - Cody
- dump resistor
- magnetic field
- upgrade to higher current
- EPICS <--> PLC communications - Wesley
- Final A-B equipment order - Elliott
- Wiring and testing controls racks - Scot
- how much testing can be done in F117?
- how much needs the PLC?
- PLC programming status - Mark W
- C-glass calibrations - Elliott
- HMI and EWEB programming - Yi, Elliott
- 25 screen limit
- dual-monitors
- Installation status - George
- Coil repair status - George