Attendees: | Attendees: | ||
− | + | # BCAL | |
+ | ## Construction | ||
### All equipment operating nominally. Builds growing within tolerances. | ### All equipment operating nominally. Builds growing within tolerances. | ||
### Mod 04 to RMS today or tomorrow; Mod 05 at 50%, Mod 06 at 10%. Two new crates arrived yesterday. | ### Mod 04 to RMS today or tomorrow; Mod 05 at 50%, Mod 06 at 10%. Two new crates arrived yesterday. |
Revision as of 12:14, 4 March 2010
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone in CC F326 is 757-269-6337
- Phone in the Regina Videoconference Suite is 306-585-4204
- Phone only if requested:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Phone line by request only.
Contents
Items for followup from previous meeting(s)
- Calibration/Monitoring
- Geometry for inputing monitoring sources into Bcal (Media:mom_gamma_log.png)
- Fcal
- Specify the number of Rad Hard blocks to writeup a change request to the project.
- Investigate mechanical issues associated with supporting lead glass on top of shashlyk modules (Lubomir, Serguei). Will to send drawings of the modules.
- Bcal
- Specify the normalization and dynamic range for the number of photons/GeV in showers
- Decide on specific grouping for SiPM sums
- Possibility of using air gap for SiPM coupling
- Finalize shapes of "Winston guides"
- Simulations:
- List of energies and angles to be simulated for the purpose of establishing the dynamic range of light to the SiPMs.
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration/Monitoring
- Light sources in Bcal
- Project schedule
- FCAL activity Fab monitoring system 15222080 (delayed by a year in Oct)
- BCAL activity Proc aux equipment incl. calibration 15221055
- FCAL
- Radiation Damage Inserts
- Shashlyk option
- Procurement Contract
- EVMS reporting and project schedule
- Scheduling the Fcal Fabrication Readiness Review
- Update on FEU-84-3 PMTs slides
- Radiation Damage Inserts
- BCAL
- Construction Status
- Fibre tests Media:Shipments8and9plots.pdf
- BCAL Readout
- Simulations
- SiPMs
- Geometry for guides, sensors, cooling and cables
- Update on USM MOU
- Other business
Minutes
Attendees:
- BCAL
- Construction
- All equipment operating nominally. Builds growing within tolerances.
- Mod 04 to RMS today or tomorrow; Mod 05 at 50%, Mod 06 at 10%. Two new crates arrived yesterday.
- Mod 02 and 03 machining most likely finished.
- Lead tally nearly done; some discrepancies. Will communicate with JLab and Vulcan today.
- Enough epoxy for 2.5 months on hand, 9 gallons back ordered.
- Shipping insurance sorted out and waiting to meet with shippers and get new quotations.
- Fibres
- Shipment 8 done and 100 fibres from No. 9 (see above links).
- Construction