Line 27: | Line 27: | ||
*** Fabrication of calorimeter prototypes (EEL126) | *** Fabrication of calorimeter prototypes (EEL126) | ||
*** Testing ECAL dividers (EEL118) (approved in January) | *** Testing ECAL dividers (EEL118) (approved in January) | ||
− | |||
** Installation of the LMS | ** Installation of the LMS | ||
*** 1053 fibers have been installed [https://logbooks.jlab.org/entry/4259134] [https://logbooks.jlab.org/entry/4262988] | *** 1053 fibers have been installed [https://logbooks.jlab.org/entry/4259134] [https://logbooks.jlab.org/entry/4262988] | ||
Line 33: | Line 32: | ||
** Power installation on the platform has been completed [https://logbooks.jlab.org/entry/4262698] | ** Power installation on the platform has been completed [https://logbooks.jlab.org/entry/4262698] | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | *** (links from the previous meetings [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]) | ||
+ | |||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Revision as of 09:46, 21 March 2024
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV short cables: received, checked, labeled (last week)
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 500 cables in total
- - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
- Ongoing projects -- Sasha / Vlad / Hakob / Laveen
- Testing of PMT dividers -- Sasha / Vlad / George
- - Testing procedure [6]
- - About 1420 dividers have been fabricated (Chris, Armen, Mindy)
- - Started removing power regulators on the newly fabricated dividers
- - George has tested 54 dividers (919 have been tested in total) [7].
- - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Preparing safety documents. The following ePASes have been submitted and approved -- Sasha and Vlad
- Installation of the ECAL LMS
- Installation of cables and dividers,
- Beam tests with the PS test setup
- Preparing ECAL cables (EEL126)
- Fabrication of calorimeter prototypes (EEL126)
- Testing ECAL dividers (EEL118) (approved in January)
- Installation of the LMS
- Cable and divider installation [10][11][12]
- Power installation on the platform has been completed [13]
- Detector installation page
- Preparing safety documents. The following ePASes have been submitted and approved -- Sasha and Vlad
- Analysis/Simulation