Difference between revisions of "JEF meeting, December 1, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 19: | Line 19: | ||
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done | *** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done | ||
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg Modules for prototype (25 are ready)] - done | *** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg Modules for prototype (25 are ready)] - done | ||
− | ** - Preparation of the LMS | + | ** - Preparation of the LMS |
− | *** - | + | *** - All fibers have been glued to the mounting plate, which will be attached to the integrating sphere. The plate was machined and polised [https://logbooks.jlab.org/entry/4228633] |
− | + | *** - Need to install light tight covers on the plastic caps. The fibers will be ready for installation after that. | |
− | + | ||
− | + | ||
− | *** - The | + | |
** - Install labels on the detector [https://halldweb.jlab.org/detectors/fcal2/lms/detector_label.jpg] | ** - Install labels on the detector [https://halldweb.jlab.org/detectors/fcal2/lms/detector_label.jpg] | ||
** - Installation of the trigger and readout electronics | ** - Installation of the trigger and readout electronics |
Revision as of 10:16, 1 December 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
- - signal patch panels are ready [1]
- - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
- - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
- - LV cables: ordered, lead time unclear
- - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- - Testing and labeling cables (Recently labeled cables in boxes)[2]
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
- Wrapped crystals - done
- Parts for TAC[4] - done
- Modules for prototype (25 are ready) - done
- - Preparation of the LMS
- - All fibers have been glued to the mounting plate, which will be attached to the integrating sphere. The plate was machined and polised [5]
- - Need to install light tight covers on the plastic caps. The fibers will be ready for installation after that.
- - Install labels on the detector [6]
- - Installation of the trigger and readout electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
- Analysis/Simulation
- Added new JEF simulation page to wiki
- Rate simulation studies