** Quite a few mu-metal housings are tight (no space for kapton film) have to be 'polished', met with Tim | ** Quite a few mu-metal housings are tight (no space for kapton film) have to be 'polished', met with Tim | ||
* Module fabrication -- Sasha | * Module fabrication -- Sasha | ||
− | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf Modules fabricated by Arshak and Sasha | + | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf Modules fabricated by Arshak and Sasha] [https://docs.google.com/document/d/1upI9M_RNR4qipzwg-SmxmzkqoCDU294x7Y3jT5M6DVY/edit (list on Google Drive)] (grand total 115, fabricated in about a month) |
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/2_17_22/fab_mod_2_17_22.jpg Fabricated modules in TEDF ] | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/2_17_22/fab_mod_2_17_22.jpg Fabricated modules in TEDF ] | ||
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] |
Revision as of 22:13, 3 March 2022
Meeting time and location
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation for mass production of FCAL2 modules -- Sasha
- DSG has preshaped more than 200 ESR foils, had a meeting today regarding wrapping crystals
- Olga visited JLab: prepared 3 sets of Silicon cookies and tested diameter of about 300 PMTs
- quite a few PMTs have to be exchanged with NPS
- Two fixtures (42 cookies in each) and digital scales have been ordered. The loan agreement with GWU will be submitted for approval in the beginning of next week.
- Some backlog with brazing straps, communicated with Tim and Mark regarding getting Chris more involved.
- Quite a few mu-metal housings are tight (no space for kapton film) have to be 'polished', met with Tim
- Module fabrication -- Sasha
- Modules fabricated by Arshak and Sasha (list on Google Drive) (grand total 115, fabricated in about a month)
- Fabricated modules in TEDF
- Status of fabrication
- Light Monitoring System
- COMCAL tests, TAC running, etc.
- Data analysis
- Simulations