Difference between revisions of "Run Planning Meeting Notes, September 30 - October 6, 2021"
From GlueXWiki
(→Thursday, September 30) |
(→Thursday, September 30) |
||
Line 5: | Line 5: | ||
#* Early Riser summary | #* Early Riser summary | ||
#* Owl summary | #* Owl summary | ||
− | #* Swing summary | + | #* [https://logbooks.jlab.org/entry/3914704 Swing summary] |
#* [https://logbooks.jlab.org/entry/3914472 Day summary] | #* [https://logbooks.jlab.org/entry/3914472 Day summary] | ||
#* During downtime for maintenance: | #* During downtime for maintenance: |
Revision as of 17:20, 29 September 2021
<- Back to Run Coordination Meetings:Summer2021
Thursday, September 30
- In last 24 hours:
- Early Riser summary
- Owl summary
- Swing summary
- Day summary
- During downtime for maintenance:
- BCAL pedestal calibration (Sergey)
- FCAL base replacement (Rebecca/Mark/Malte)
- Issues:
- FCAL:
- Dead channels https://logbooks.jlab.org/entry/3914386 (ig)
- 53 suspicious channels https://logbooks.jlab.org/entry/3913947 https://logbooks.jlab.org/entry/3913739 (Rebecca/Mark/Malte)
- Sweep magnet turn off https://logbooks.jlab.org/entry/3913900 (Simon)
- Bleedthrough
- FCAL:
- Plan:
- Before taking data: check radiation level and beam quality (HARP scan)
- 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
- 100 nA CDC & FDC turn off (2 shifts)
- 200 nA CDC & FDC turn off (8.4 shifts)
- Remove Be target to take empty target