Difference between revisions of "May 7, 2020 CPP Design Meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 18: | Line 18: | ||
** Alignment hardware | ** Alignment hardware | ||
** Electronics shielding [[Media:Muon_Chamber_Shielding.pdf]] | ** Electronics shielding [[Media:Muon_Chamber_Shielding.pdf]] | ||
− | ** Grounding | + | ** Grounding cutouts in steel |
** Complete structural analysis | ** Complete structural analysis | ||
** Develop installation plan | ** Develop installation plan |
Revision as of 18:00, 6 May 2020
Meeting Time and Place =
Thursday May 7, 2020, 1:30pm Bluejeans https://bluejeans.com/710246635/3638?src=calendarLink
- Present - Elton, Dave, Stephanie, Llya, Rory (remote)
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_23,_2020_CPP_Design_Meeting#Minutes_and_Action_Items
- Overall description https://halldweb.jlab.org/DocDB/0041/004180/006/CPP_update_oct19.pdf
- Design/Fab/Install schedule Media:CPP_rough_schedule.pdf
- 3D model - show progress
- Alignment tolerances require fine adjustment
- Things to work out
- 90° connector
- Gas line routing
- Procurement/installation schedule
- Alignment hardware
- Electronics shielding Media:Muon_Chamber_Shielding.pdf
- Grounding cutouts in steel
- Complete structural analysis
- Develop installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Reviewed minutes of last meeting
- Need to notch steel at bottom to clear connectors -- Stephanie
- Look at using a 90° connector -- Rory
- Check gas line bending to clear beam left dark room -- Rory
- Alignment requirements relative to BL - X&Y ±2mm, Z ±1cm
- Met with survey - need to add x,y and z adjustments for the entire system to achieve this
- Desire to have a small block of 5cm lead movable
- can be a local adjustment
- Ring with 7.5cm hole
- ok to have 10cm thick where overlap is
- Holes to be square with radius corner
- Hole size should have 1mm precision
- What should be the size of the hole in the large lead absorber?
- Need to check repeatability of detector after moving FCAL platform
- Develop a procurement plan for this FY -- Tim
- Set up new meeting in 2 weeks