Line 1: | Line 1: | ||
Present: Chris Keith, Dave Meekins, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch | Present: Chris Keith, Dave Meekins, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch | ||
− | ==Minutes from last mtg https:// | + | ==Minutes from last mtg https://halldweb.jlab.org/wiki/index.php/GlueX_Target_Design_Mtg,_Mar_26,_2014== |
==Agenda== | ==Agenda== | ||
Line 59: | Line 59: | ||
* Tim will get with Jim Dahlberg for more detail on fiducial points. | * Tim will get with Jim Dahlberg for more detail on fiducial points. | ||
* Hall D to supply cooling water for compressor and temp sensors, target group to supply return flow instrumentation. Need to set turn off temps for compressor | * Hall D to supply cooling water for compressor and temp sensors, target group to supply return flow instrumentation. Need to set turn off temps for compressor | ||
− | * Need to look at required spares some day - | + | * Need to look at required spares some day - Chris working |
* Target group will buy vacuum instrumentation | * Target group will buy vacuum instrumentation | ||
− | * need to move 4" gate valve downstream and add tee for vacuum | + | * need to move 4" gate valve downstream and add tee for vacuum instrumentation |
* James pointed out that a cover for the scattering chamber will be needed when removed from position | * James pointed out that a cover for the scattering chamber will be needed when removed from position | ||
− | * | + | * Werth from the detector group is helping Dave B. with the controls |
− | + | * Need to control start/stop of compressor (Werth to look at Labview setup) | |
− | + | * there will be a 20' long flexible gas line from the target to the vent line | |
+ | * Chris to supply list of signal names to Dave by the end of the week. | ||
+ | * Discussion on location of controls crate and magnetic field magnitude - Tim to develop location vs. mag field layouts to help make the decision on the final location for the controls. | ||
+ | * Need to fit check Start counter hub to target hub next week to ensure proper mating | ||
==Action Items== | ==Action Items== |
Latest revision as of 15:16, 31 March 2015
Present: Chris Keith, Dave Meekins, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch
Contents
Minutes from last mtg https://halldweb.jlab.org/wiki/index.php/GlueX_Target_Design_Mtg,_Mar_26,_2014
Agenda
- Where are we now? Media:Target labor.pdf
- Cryo hardware status
- Gas system status
- Exhaust from pressure relief
- Plumbing on cart
- pressure system documentation
- Storage tanks
- 3D model/drawings Media:Target assy.pdf
- Target/Start counter interface
- Vacuum system update
- Flange config
- Controls status
- updated P&I
- changes for subcooled config
- Installation cart update Media:Target cart.jpg
- Tank config
- Lifting
- Controls/panel config
- Alignment features
- Scattering chamber status
- Cell Fabrication Status
- thermometry
- Spare cell
- Schedule
- Readiness review
- Assy/test in EEL
- Install/test in Hall
Info
- P&I Diagram Media:Target P&I.pdf
- Controls logic Media:Target controls.pdf
- Dave's SOW Media:Target new SOW.pdf
- Dave's Calcs Media:Target calcs1.pdf Media:Target calcs2.pdf
- Dave's FMEA Media:Target latest FMEA.pdf
Minutes
- James fabricating new cell with straight torlon base and aluminized Kapton(plus a spare) - parts due in this week
- Target group fabricating an interlock box to hard wire turn off the compressor - Dave Griffith
- Ok to put kill button in counting room for Target
- (2) 55 gallon Tanks are in
- Target group will procure one additional relief valve - 1 relief on each tank and 2 on gas panel
- Vent stack materials defined and on order - Hall D to assemble
- Joe Beaufeit to verify compressor power and ensure it is supplied in Hall D
- May 8th safety review - Tim to send proposal to Patrizia for agenda and pre-brief
- 5mil kapton window between target and upstream beamline is acceptable
- 4" gate valve (on order) and turbo for pumping on vacuum chamber and 1.5" valve on beamline (both in house) supplied by Hall D
- Target group will supply a diaphragm switch hard wired to turn turbo off
- Tim/Mark to meet with Fernando to determine start counter cabling/patch panel config.
- Vacuum chamber bottom flange to include 4" pump port and 4 - 2 3/4" conflat ports on order (Matt to check with Dave Meekins if class C ok)
- Chris sent email to Javier outlining responsibilities
- Hall D will deliver assembled cart to target group this week. It will have mounts for tanks but the target adjustment cartridges will not be available until next week
- Tim will get with Jim Dahlberg for more detail on fiducial points.
- Hall D to supply cooling water for compressor and temp sensors, target group to supply return flow instrumentation. Need to set turn off temps for compressor
- Need to look at required spares some day - Chris working
- Target group will buy vacuum instrumentation
- need to move 4" gate valve downstream and add tee for vacuum instrumentation
- James pointed out that a cover for the scattering chamber will be needed when removed from position
- Werth from the detector group is helping Dave B. with the controls
- Need to control start/stop of compressor (Werth to look at Labview setup)
- there will be a 20' long flexible gas line from the target to the vent line
- Chris to supply list of signal names to Dave by the end of the week.
- Discussion on location of controls crate and magnetic field magnitude - Tim to develop location vs. mag field layouts to help make the decision on the final location for the controls.
- Need to fit check Start counter hub to target hub next week to ensure proper mating